{"id":24358,"date":"2022-09-30T16:44:57","date_gmt":"2022-09-30T13:44:57","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=24358"},"modified":"2024-06-20T13:54:26","modified_gmt":"2024-06-20T10:54:26","slug":"september-2022","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=24358&lang=en","title":{"rendered":"SEPTEMBER 2022"},"content":{"rendered":"<p><strong><u>TZAVELA Shaft<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Architectural finishes \u2013 Painting works at the staircase (walls, floors).<\/li>\n<li>Construction of sound absorbing plaster.<\/li>\n<li>Installation of staircase balustrades and balustrades at the street level staircase.<\/li>\n<li>Installation of the entrance hatch at street level.<\/li>\n<li>Installation of roller shutters.<\/li>\n<li>Reinstatement of Tzavela and Lakonias Streets, opening to the<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Restoration of minor deficiencies.<\/li>\n<\/ul>\n<p><strong><u>MANIATIKA STATION<\/u><\/strong><\/p>\n<p><strong><u>STATION\u2019s OPEN CUT <\/u><\/strong><strong>\u00a0\u00a0\u00a0\u00a0\u00a0<\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Surface reinstatement (construction of road pavement and sidewalks at Mavromichali Street).<\/li>\n<li>Installation of glass panels at levels -1, -2.<\/li>\n<li>Door painting works.<\/li>\n<li>Installation of lifts at street level and at level -2.<\/li>\n<li>Installation of lighting poles at the sidewalk of Etolikou Street.<\/li>\n<li>Reinstatement of road pavement in Mavromichali Street.<\/li>\n<li>Architectural finishes \u2013 Re-painting works at walls and floors at levels -4, -3, -2, -1, reinstatement of concrete surfaces, re-painting works of parapet walls at street level.<\/li>\n<li>Installation of steel cladding (panels) on the walls\/ceilings and of metal side covers at the station\u2019s escalators.<\/li>\n<li>Installation of stainless steel handrails.<\/li>\n<li>Installation of the station\u2019s signage.<\/li>\n<li>Construction of partition walls at the station\u2019s south expropriation limits (street level)<\/li>\n<li>Surface reinstatement (construction of road pavement and sidewalks at Etolikou Street)<\/li>\n<li>Slab paving works and installation of paving stones and lighting at street level.<\/li>\n<li>Laying of planting soil, planting of trees, bushes and lawn at the station\u2019s flower beds.<\/li>\n<li>Connection of the station with EYDAP network.<\/li>\n<li>Installation of waste bins, seats (benches), bicycle-motorcycle stands at the square.<\/li>\n<li>Removal of worksite fences.<\/li>\n<li>Installation of traffic signs and removal of temporary signs that had been installed due to traffic diversions.<\/li>\n<li>Opening to the traffic of Etolikou, Koumoundourou, Dimitrakopoulou, Gythiou and Mavromichali Streets.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Restoration of minor deficiencies.<\/li>\n<\/ul>\n<p><strong><u>MAIN TUNNEL OF THE STATION (<\/u><\/strong><strong><u>\u039d\u0391\u03a4\u039c<\/u><\/strong><strong><u>)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Steel cladding on the roof and side covers.<\/li>\n<li>Installation of information boards and signage at the platforms.<\/li>\n<li>Installation of seats at the platforms.<\/li>\n<li>Installation of radio communication (TETRA) cable.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Restoration of minor deficiencies.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND NATM SECTIONS OF THE STATION (NATM)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Installation of granites and stainless ducts (gutters).<\/li>\n<li>Installation of lining (made of steel and gypsum boards) at the access tunnels of the station.<\/li>\n<li>Installation of lifts glass panes.<\/li>\n<li>Installation of metal side covers and handrails at the station\u2019s escalators.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Restoration of minor deficiencies.<\/li>\n<\/ul>\n<p><strong><u>SOUTH VENTILATION SHAFT OF THE STATION<\/u><\/strong> (Koumoundourou Street)<\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Construction of perimeter wall at the boundaries of the expropriation.<\/li>\n<li>Construction of metal structures at K.P. +8.36 and +21.00.<\/li>\n<li>Construction of sound absorbing plaster.<\/li>\n<li>Installation of staircase balustrades &#8211; handrails.<\/li>\n<li>Architectural finishes (re-painting works).<\/li>\n<li>Door painting works.<\/li>\n<li>Installation of access hatch at the street level.<\/li>\n<li>Road surface reinstatement, opening to traffic of Koumoundourou Street, installation of lighting bollards, waste bins and seats.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Restoration of minor deficiencies.<\/li>\n<\/ul>\n<p><strong><u>NORTH VENTILATION SHAFT OF THE STATION<\/u><\/strong> (Dimitrakopoulou Street)<\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Installation of metal structures at K.P. +8.08 and +24.98.<\/li>\n<li>Construction of sound absorbing plaster.<\/li>\n<li>Architectural finishes (re-painting works).<\/li>\n<li>Door painting works.<\/li>\n<li>Installation of staircase balustrades &#8211; handrails.<\/li>\n<li>Installation of the entrance hatch at street level.<\/li>\n<li>Construction of perimeter parapet walls at the boundary of the expropriation.<\/li>\n<li>Road surface reinstatement, opening to traffic of Dimitrakopoulou Street, installation of lighting bollards, waste bins, and seats and planting of trees.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Restoration of minor deficiencies.<\/li>\n<\/ul>\n<p><strong><u>MELA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Painting works at the staircase and the remaining areas.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Still pending is the reinstatement of the square\u2019s area that had been occupied.<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS<\/u><\/strong><strong><u> STATION<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Painting works at the station.<\/li>\n<li>Construction of fillings and industrial floors.<\/li>\n<li>Installation of metal doors.<\/li>\n<li>Installation of granites.<\/li>\n<li>Walls and columns lining.<\/li>\n<li>Installation of false ceilings.<\/li>\n<li>Installation of galvanized metal panels.<\/li>\n<li>Backfilling of entrances.<\/li>\n<li>Installation of lifts.<\/li>\n<li>Construction of sidewalks and installation of granites and marbles at street level.<\/li>\n<li>Construction of sub-base and asphalt laying works.<\/li>\n<li>Planting works and installation of irrigation system.<\/li>\n<li>Installation of trays at street level.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Reinstatement of ISAP area.<\/li>\n<li>Reinstatement of OLP area.<\/li>\n<\/ul>\n<p><strong><u>ROLOI SHAFT &amp; NATM ACCESS TUNNEL<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<li>Installation of emergency exit hatch at street level.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO STATION <\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE <\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 <\/strong><\/p>\n<ul>\n<li>Opening of V. Georgiou and Karaiskou Streets to the traffic.<\/li>\n<li>Installation of false ceiling at the ticketing level and at the platform level.<\/li>\n<li>Installation of floor granites at the ticketing level.<\/li>\n<li>Construction of stainless cladding, stanchion and balustrades at the ticketing level, at the platform level and the staircases.<\/li>\n<li>Installation of ironmongery on the doors.<\/li>\n<li>Conservation of the Project\u2019s archaeological finds.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><strong>The following works are in progress<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Reinstatement at street level (slab paving works, planting works, irrigation network for planting areas etc.).<\/li>\n<li>Painting of the floor of the mechanical level and re-painting works of the walls of the technical rooms<\/li>\n<\/ul>\n<p><strong><u>STAIRCASE GALLERIES<\/u><\/strong><\/p>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of supports and wall and ceiling panels.<\/li>\n<li>Installation of handrails at the staircases.<\/li>\n<li>Installation of floor granites.<\/li>\n<\/ul>\n<p><strong><u>KORAI SQUARE ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Construction of lift housing structure at street level.<\/li>\n<li>Removal of worksite offices from the surface level.<\/li>\n<li>Installation of wall and ceiling panels.<\/li>\n<li>Implementation of the design for the display of the archaeological finds in the recess.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Reinstatement at street level.<\/li>\n<\/ul>\n<p><strong><u> BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of wall and ceiling panels.<\/li>\n<li>Implementation of the design for the display of the archaeological finds in the recess.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO VENTILATION SHAFT<\/u><\/strong><strong><u> (<\/u><\/strong><strong><u>RALLIOS SHAFT) AND VENTILATION GALLERY<\/u><\/strong><strong>\u00a0 \u00a0 \u00a0<\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<li>Sidewalk traffic reinstatement on V. Georgiou Street.<\/li>\n<li>Removal of sidewalk in the framework of the implementation of the permanent traffic study.<\/li>\n<li>Painting of the floor of the connecting tunnel.<\/li>\n<\/ul>\n<p><strong><u>TRIPLE TRACK NATM TUNNEL<\/u><\/strong><\/p>\n<p>Works have been completed<strong>.<\/strong><\/p>\n<p><strong><u>DELIGIANNI SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Disassembly of building crane.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Reinstatement at street level.<\/li>\n<\/ul>\n<p><strong><u>PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Reinstatement at street level.<\/li>\n<\/ul>\n","protected":false},"excerpt":{"rendered":"<p>TZAVELA Shaft The following works have been completed: Architectural finishes \u2013 Painting works at the staircase (walls, floors). Construction of sound absorbing plaster. Installation of staircase balustrades and balustrades at the street level staircase. Installation of the entrance hatch at street level. Installation of roller shutters. Reinstatement of Tzavela and Lakonias Streets, opening to the The following works are in progress: Restoration of minor deficiencies. MANIATIKA STATION STATION\u2019s OPEN CUT \u00a0\u00a0\u00a0\u00a0\u00a0 The following works have been completed: Surface reinstatement (construction of road pavement and sidewalks at Mavromichali Street). Installation of glass panels at levels -1, -2. Door painting works. Installation of lifts at street level and at level -2. Installation of lighting poles at the sidewalk of Etolikou Street. Reinstatement of road pavement in Mavromichali Street. Architectural finishes \u2013 Re-painting works at walls and floors at levels -4, -3, -2, -1, reinstatement of concrete surfaces, re-painting works of parapet walls at street level. Installation of steel cladding (panels) on the walls\/ceilings and of metal side covers at the station\u2019s escalators. Installation of stainless steel handrails. Installation of the station\u2019s signage. Construction of partition walls at the station\u2019s south expropriation limits (street level) Surface reinstatement (construction of road pavement and sidewalks at Etolikou Street) Slab paving works and installation of paving stones and lighting at street level. Laying of planting soil, planting of trees, bushes and lawn at the station\u2019s flower beds. Connection of the station with EYDAP network. Installation of waste bins, seats (benches), bicycle-motorcycle stands at the square. Removal of worksite fences. Installation of traffic signs and removal of temporary signs that had been installed due to traffic diversions. Opening to the traffic of Etolikou, Koumoundourou, Dimitrakopoulou, Gythiou and Mavromichali Streets. The following works are in progress: Restoration of minor deficiencies. MAIN TUNNEL OF THE STATION (\u039d\u0391\u03a4\u039c) The following works have been completed: Steel cladding on the roof and side covers. Installation of information boards and signage at the platforms. Installation of seats at the platforms. Installation of radio communication (TETRA) cable. The following works are in progress: Restoration of minor deficiencies. UNDERGROUND NATM SECTIONS OF THE STATION (NATM) The following works have been completed: Installation of granites and stainless ducts (gutters). Installation of lining (made of steel and gypsum boards) at the access tunnels of the station. Installation of lifts glass panes. Installation of metal side covers and handrails at the station\u2019s escalators. The following works are in progress: Restoration of minor deficiencies. SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street) The following works have been completed: Construction of perimeter wall at the boundaries of the expropriation. Construction of metal structures at K.P. +8.36 and +21.00. Construction of sound absorbing plaster. Installation of staircase balustrades &#8211; handrails. Architectural finishes (re-painting works). Door painting works. Installation of access hatch at the street level. Road surface reinstatement, opening to traffic of Koumoundourou Street, installation of lighting bollards, waste bins and seats. The following works are in progress: Restoration of minor deficiencies. NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street) The following works have been completed: Installation of metal structures at K.P. +8.08 and +24.98. Construction of sound absorbing plaster. Architectural finishes (re-painting works). Door painting works. Installation of staircase balustrades &#8211; handrails. Installation of the entrance hatch at street level. Construction of perimeter parapet walls at the boundary of the expropriation. Road surface reinstatement, opening to traffic of Dimitrakopoulou Street, installation of lighting bollards, waste bins, and seats and planting of trees. The following works are in progress: Restoration of minor deficiencies. MELA SHAFT The following works have been completed: Painting works at the staircase and the remaining areas. The following works are in progress: Still pending is the reinstatement of the square\u2019s area that had been occupied. PIRAEUS STATION The following works have been completed: Painting works at the station. Construction of fillings and industrial floors. Installation of metal doors. Installation of granites. Walls and columns lining. Installation of false ceilings. Installation of galvanized metal panels. Backfilling of entrances. Installation of lifts. Construction of sidewalks and installation of granites and marbles at street level. Construction of sub-base and asphalt laying works. Planting works and installation of irrigation system. Installation of trays at street level. The following works are in progress: Reinstatement of ISAP area. Reinstatement of OLP area. ROLOI SHAFT &amp; NATM ACCESS TUNNEL The following works have been completed: Sealing of the temporary pumping station. Installation of emergency exit hatch at street level. DIMOTIKO THEATRO STATION MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE The following works have been completed:\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 Opening of V. Georgiou and Karaiskou Streets to the traffic. Installation of false ceiling at the ticketing level and at the platform level. Installation of floor granites at the ticketing level. Construction of stainless cladding, stanchion and balustrades at the ticketing level, at the platform level and the staircases. Installation of ironmongery on the doors. Conservation of the Project\u2019s archaeological finds. \u00a0The following works are in progress: Reinstatement at street level (slab paving works, planting works, irrigation network for planting areas etc.). Painting of the floor of the mechanical level and re-painting works of the walls of the technical rooms STAIRCASE GALLERIES The following works are in progress: Installation of supports and wall and ceiling panels. Installation of handrails at the staircases. Installation of floor granites. KORAI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Construction of lift housing structure at street level. Removal of worksite offices from the surface level. Installation of wall and ceiling panels. Implementation of the design for the display of the archaeological finds in the recess. The following works are in progress: Reinstatement at street level. BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY The following works are in progress: Installation of wall and ceiling panels. Implementation of the design for the display of the archaeological finds in the recess. DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY\u00a0 \u00a0 \u00a0 The following works have been completed: Sealing of the temporary pumping station. Sidewalk traffic reinstatement on V. Georgiou Street. Removal of sidewalk in the framework of the implementation of the permanent traffic study. Painting of the floor of the connecting tunnel. TRIPLE TRACK NATM TUNNEL Works have been completed. DELIGIANNI SHAFT The following works have been completed: Disassembly of building crane. The following works are in progress: Reinstatement at street level. PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL The following works are in progress: Reinstatement at street level.<\/p>\n","protected":false},"author":8,"featured_media":24350,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-24358","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-scaled.jpg",2560,1920,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-scaled.jpg",2560,1920,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-scaled.jpg",2560,1920,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-300x225.jpg",300,225,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-1024x768.jpg",960,720,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-1536x1152.jpg",1536,1152,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-2048x1536.jpg",2048,1536,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-1140x855.jpg",1140,855,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/10\/AM_Dimotiko-Theatro_Sept-2022-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"ivassalos","author_link":"https:\/\/www.emetro.gr\/?author=8"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"TZAVELA Shaft The following works have been completed: Architectural finishes \u2013 Painting works at the staircase (walls, floors). Construction of sound absorbing plaster. Installation of staircase balustrades and balustrades at the street level staircase. Installation of the entrance hatch at street level. Installation of roller shutters. Reinstatement of Tzavela and Lakonias Streets, opening to the&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/24358","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/8"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=24358"}],"version-history":[{"count":2,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/24358\/revisions"}],"predecessor-version":[{"id":24360,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/24358\/revisions\/24360"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/24350"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=24358"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=24358"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=24358"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}