{"id":23518,"date":"2022-06-16T13:54:15","date_gmt":"2022-06-16T10:54:15","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=23518"},"modified":"2024-06-20T13:59:01","modified_gmt":"2024-06-20T10:59:01","slug":"may-2022","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=23518&lang=en","title":{"rendered":"MAY 2022"},"content":{"rendered":"<p><strong><u>TZAVELA Shaft<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Architectural finishes \u2013 Painting works at the staircase (walls, floors).<\/li>\n<li>Construction of sound absorbing plaster.<\/li>\n<li>Installation of staircase balustrades and balustrades at the street-level staircase.<\/li>\n<li>Installation of the entrance hatch at street level.<\/li>\n<li>Reinstatement of Tzavela and Lakonias Streets, opening to the<\/li>\n<\/ul>\n<p><strong><u>MANIATIKA STATION<\/u><\/strong><\/p>\n<p><strong><u>STATION\u2019s OPEN CUT <\/u><\/strong><strong>\u00a0\u00a0\u00a0\u00a0\u00a0<\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Construction of partition walls at the station\u2019s expropriation limits (street level).<\/li>\n<li>Surface reinstatement (construction of road pavement and sidewalk at Mavromichali Street).<\/li>\n<li>Installation of glass panels at levels -1, -2.<\/li>\n<li>Door painting works.<\/li>\n<li>Installation of lifts at street level and at level -2.<\/li>\n<li>Installation of lighting poles at the sidewalk of Etolikou Street.<\/li>\n<li>Reinstatement of road pavement in Mavromichali Street at the west of the station.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Architectural finishes \u2013 Painting works at walls at levels -4, -3, -2, -1, reinstatement of concrete surfaces, preparation works for the painting of parapet walls at street level.<\/li>\n<li>Installation of false ceilings and steel cladding (panels) on the walls of the main areas at the station\u2019s level -1.<\/li>\n<li>Construction of flower beds\u2019 walls, slab paving works and installation of paving stones and lighting at street level.<\/li>\n<li>Laying of planting soil at the station\u2019s flower beds.<\/li>\n<\/ul>\n<p><strong><u>MAIN TUNNEL OF THE STATION (<\/u><\/strong><strong><u>\u039d\u0391\u03a4\u039c<\/u><\/strong><strong><u>)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Steel cladding on the roof and.<\/li>\n<li>Installation of information boards and signage at the platforms.<\/li>\n<li>Installation of seats at the platforms.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND NATM SECTIONS OF THE STATION (NATM)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Installation of granites and stainless ducts (gutters).<\/li>\n<li>Installation of lining (made of steel and gypsum boards) at the access tunnels of the station.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of steel lining at the upper transverse access gallery.<\/li>\n<li>Installation of glass panes in lifts.<\/li>\n<\/ul>\n<p><strong><u>SOUTH VENTILATION SHAFT OF THE STATION<\/u><\/strong><strong> (<\/strong>Koumoundourou Street)<\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Construction of perimeter wall at the boundaries of the expropriation.<\/li>\n<li>Construction of metal structures at K.P. +8.36 and +21.00.<\/li>\n<li>Construction of sound absorbing plaster.<\/li>\n<li>Installation of staircase balustrades &#8211; handrails.<\/li>\n<li>Architectural finishes (painting works).<\/li>\n<li>Door painting works.<\/li>\n<li>Installation of access hatch at the street level.<\/li>\n<li>Road surface reinstatement at Koumoundourou Street, installation of lighting bollards.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Surface reinstatement (surrounding area).<\/li>\n<\/ul>\n<p><strong><u>NORTH VENTILATION SHAFT OF THE STATION<\/u><\/strong> (Dimitrakopoulou Street)<\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Installation of metal structures at K.P. +8.08 and +24.98.<\/li>\n<li>Construction of sound absorbing plaster.<\/li>\n<li>Architectural finishes (painting works).<\/li>\n<li>Door painting works.<\/li>\n<li>Installation of staircase balustrades &#8211; handrails.<\/li>\n<li>Installation of the entrance hatch at street level.<\/li>\n<li>Construction of perimeter wall at the boundary of the expropriation.<\/li>\n<li>Road surface reinstatement at Dimitrakopoulou Street, installation of lighting bollards.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Surface reinstatement (construction of sidewalk and of surrounding area).<\/li>\n<\/ul>\n<p><strong><u>MELA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of pit.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Construction of rainwater network.<\/li>\n<li>Construction of the sidewalk of P. Mela Street.<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS<\/u><\/strong><strong><u> STATION<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of main station.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Construction of architectural finishes (installation of glass panes at the ticketing level (-1), filling works at level -1, installation of granites at levels -1 and -3, construction of masonry and plastering works in access 3 at level -1, installation of false ceiling at level -1 and -3, painting works at levels -1 and -2, at the staircases and at track level, wall and column cladding works at level -3 and side coverings at the public staircases, installation of handrails and balustrades at the staircases), works in the LAS, RS areas.<\/li>\n<li>Works for the extension of the sidewalk in Akti Kallimassioti.<\/li>\n<li>Electromechanical works at levels -1 and -2 and installation of air exhaust duct at the platforms\u2019 level (-3).<\/li>\n<li>Waterproofing of access 3 at the roof slab, of the lift and the access 3 tunnel.<\/li>\n<li>Concreting of exterior and interior parapet walls, roof slab, staircase, lift and tunnel walls and parapet walls at street level in access 3.<\/li>\n<li>Concreting works at the lift of access1 and at the connecting tunnel.<\/li>\n<li>Demolition of pile cap beam adjacent to accesses 1 and 2.<\/li>\n<li>Works for the construction of rainwater network.<\/li>\n<li>Backfilling works for bringing back the street above station level.<\/li>\n<li>Removal of struts in access 3.<\/li>\n<li>Installation of ILPAP poles.<\/li>\n<\/ul>\n<p><strong><u>ROLOI SHAFT &amp; NATM ACCESS TUNNEL<\/u><\/strong><\/p>\n<p><strong>\u00a0<\/strong><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<li>Installation of emergency exit hatch at street level.<\/li>\n<\/ul>\n<p><strong><u>The following works are in progress:<\/u><\/strong><\/p>\n<p>Painting of industrial floor at the connecting tunnel and at the floor of the shaft..<\/p>\n<p><strong><u>DIMOTIKO THEATRO STATION <\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE <\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 <\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<li>Traffic reinstatement at V. Georgiou Street.<\/li>\n<li>Traffic reinstatement at Karaiskou Street.<\/li>\n<\/ul>\n<p><strong>The following works are in progress<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Reinstatement at street level (construction of inner parapet walls at the square, marble cladding works in the square, backfilling works in the flower beds, construction of water fountains).<\/li>\n<li>Installation of false ceiling at the ticketing level.<\/li>\n<li>Installation of floor granites at the mechanical floor, at the ticketing level and at the platform level.<\/li>\n<li>Painting of the floor at staircase no. 7.<\/li>\n<li>Construction of card issuing machine bases at the ticketing level.<\/li>\n<li>Painting works in areas 2.1, 2.2, 2.7, 1.8.2 of the ticketing level.<\/li>\n<li>Construction of fire-rated glass panes at platform level.<\/li>\n<li>Installation of wall panels at the platform level.<\/li>\n<li>Installation of wall-mounted granites at the platform level.<\/li>\n<li>Installation of stainless steel cladding at platform level.<\/li>\n<li>Painting works in platform fronts (track level).<\/li>\n<li>Conservation of the Project\u2019s archaeological finds.<\/li>\n<\/ul>\n<p><strong><u>STAIRCASE GALLERIES<\/u><\/strong><\/p>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of supports and wall and ceiling panels.<\/li>\n<\/ul>\n<p><strong><u>KORAI SQUARE ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Construction of lift housing structure at street level.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of supports for the wall and ceiling panels according to the design for the display of the archaeological finds.<\/li>\n<li>Implementation of the design for the display of the archaeological finds.<\/li>\n<\/ul>\n<p><strong><u> BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of supports for the wall and ceiling panels according to the design for the display of the archaeological finds.<\/li>\n<li>Installation of the floor glass panes in the antiquities recess.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO VENTILATION SHAFT<\/u><\/strong><strong><u> (<\/u><\/strong><strong><u>RALLIOS SHAFT) AND VENTILATION GALLERY<\/u><\/strong><strong>\u00a0<\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<li>Sidewalk traffic reinstatement on V. Georgiou Street.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><strong><u>TRIPLE TRACK NATM TUNNEL<\/u><\/strong><\/p>\n<p>Works have been completed<strong>.<\/strong><\/p>\n<p><strong><u>DELIGIANNI SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Disassembly of building crane.<\/li>\n<\/ul>\n<p><strong>The following works are pending:<\/strong><\/p>\n<ul>\n<li>Demolition of pile cap beam.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Construction of inner parapet walls at the square.<\/li>\n<li>Backfilling-compaction works.<\/li>\n<\/ul>\n<p><strong><u>PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Demolition of concrete at surface level.<\/li>\n<li>Polyurethane injections at the connecting tunnel and the shaft.<\/li>\n<li>Disassembly of building crane.<\/li>\n<li>Installation of balustrades at the staircase.<\/li>\n<li>Excavation works on Deligianni Street for the connection of the shaft with the sewage network.<\/li>\n<\/ul>\n","protected":false},"excerpt":{"rendered":"<p>TZAVELA Shaft The following works have been completed: Architectural finishes \u2013 Painting works at the staircase (walls, floors). Construction of sound absorbing plaster. Installation of staircase balustrades and balustrades at the street-level staircase. Installation of the entrance hatch at street level. Reinstatement of Tzavela and Lakonias Streets, opening to the MANIATIKA STATION STATION\u2019s OPEN CUT \u00a0\u00a0\u00a0\u00a0\u00a0 The following works have been completed: Construction of partition walls at the station\u2019s expropriation limits (street level). Surface reinstatement (construction of road pavement and sidewalk at Mavromichali Street). Installation of glass panels at levels -1, -2. Door painting works. Installation of lifts at street level and at level -2. Installation of lighting poles at the sidewalk of Etolikou Street. Reinstatement of road pavement in Mavromichali Street at the west of the station. \u00a0The following works are in progress: Architectural finishes \u2013 Painting works at walls at levels -4, -3, -2, -1, reinstatement of concrete surfaces, preparation works for the painting of parapet walls at street level. Installation of false ceilings and steel cladding (panels) on the walls of the main areas at the station\u2019s level -1. Construction of flower beds\u2019 walls, slab paving works and installation of paving stones and lighting at street level. Laying of planting soil at the station\u2019s flower beds. MAIN TUNNEL OF THE STATION (\u039d\u0391\u03a4\u039c) The following works have been completed: Steel cladding on the roof and. Installation of information boards and signage at the platforms. Installation of seats at the platforms. UNDERGROUND NATM SECTIONS OF THE STATION (NATM) The following works have been completed: Installation of granites and stainless ducts (gutters). Installation of lining (made of steel and gypsum boards) at the access tunnels of the station. The following works are in progress: Installation of steel lining at the upper transverse access gallery. Installation of glass panes in lifts. SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street) The following works have been completed: Construction of perimeter wall at the boundaries of the expropriation. Construction of metal structures at K.P. +8.36 and +21.00. Construction of sound absorbing plaster. Installation of staircase balustrades &#8211; handrails. Architectural finishes (painting works). Door painting works. Installation of access hatch at the street level. Road surface reinstatement at Koumoundourou Street, installation of lighting bollards. The following works are in progress: Surface reinstatement (surrounding area). NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street) The following works have been completed: Installation of metal structures at K.P. +8.08 and +24.98. Construction of sound absorbing plaster. Architectural finishes (painting works). Door painting works. Installation of staircase balustrades &#8211; handrails. Installation of the entrance hatch at street level. Construction of perimeter wall at the boundary of the expropriation. Road surface reinstatement at Dimitrakopoulou Street, installation of lighting bollards. The following works are in progress: Surface reinstatement (construction of sidewalk and of surrounding area). MELA SHAFT The following works have been completed: Concreting of pit. The following works are in progress: Construction of rainwater network. Construction of the sidewalk of P. Mela Street. PIRAEUS STATION The following works have been completed: Concreting of main station. The following works are in progress: Construction of architectural finishes (installation of glass panes at the ticketing level (-1), filling works at level -1, installation of granites at levels -1 and -3, construction of masonry and plastering works in access 3 at level -1, installation of false ceiling at level -1 and -3, painting works at levels -1 and -2, at the staircases and at track level, wall and column cladding works at level -3 and side coverings at the public staircases, installation of handrails and balustrades at the staircases), works in the LAS, RS areas. Works for the extension of the sidewalk in Akti Kallimassioti. Electromechanical works at levels -1 and -2 and installation of air exhaust duct at the platforms\u2019 level (-3). Waterproofing of access 3 at the roof slab, of the lift and the access 3 tunnel. Concreting of exterior and interior parapet walls, roof slab, staircase, lift and tunnel walls and parapet walls at street level in access 3. Concreting works at the lift of access1 and at the connecting tunnel. Demolition of pile cap beam adjacent to accesses 1 and 2. Works for the construction of rainwater network. Backfilling works for bringing back the street above station level. Removal of struts in access 3. Installation of ILPAP poles. ROLOI SHAFT &amp; NATM ACCESS TUNNEL \u00a0The following works have been completed: Sealing of the temporary pumping station. Installation of emergency exit hatch at street level. The following works are in progress: Painting of industrial floor at the connecting tunnel and at the floor of the shaft.. DIMOTIKO THEATRO STATION MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE The following works have been completed:\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 Sealing of the temporary pumping station. Traffic reinstatement at V. Georgiou Street. Traffic reinstatement at Karaiskou Street. The following works are in progress: Reinstatement at street level (construction of inner parapet walls at the square, marble cladding works in the square, backfilling works in the flower beds, construction of water fountains). Installation of false ceiling at the ticketing level. Installation of floor granites at the mechanical floor, at the ticketing level and at the platform level. Painting of the floor at staircase no. 7. Construction of card issuing machine bases at the ticketing level. Painting works in areas 2.1, 2.2, 2.7, 1.8.2 of the ticketing level. Construction of fire-rated glass panes at platform level. Installation of wall panels at the platform level. Installation of wall-mounted granites at the platform level. Installation of stainless steel cladding at platform level. Painting works in platform fronts (track level). Conservation of the Project\u2019s archaeological finds. STAIRCASE GALLERIES The following works are in progress: Installation of supports and wall and ceiling panels. KORAI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Construction of lift housing structure at street level. The following works are in progress: Installation of supports for the wall and ceiling panels according to the design for the display of the archaeological finds. Implementation of the design for the display of the archaeological finds. BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY The following works are in progress: Installation of supports for the wall and ceiling panels according to the design for the display of the archaeological finds. Installation of the floor glass panes in the antiquities recess. DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY\u00a0 The following works have been completed: Sealing of the temporary pumping station. Sidewalk traffic reinstatement on V. Georgiou Street. \u00a0TRIPLE TRACK NATM TUNNEL Works have been completed. DELIGIANNI SHAFT The following works have been completed: Disassembly of building crane. The following works are pending: Demolition of pile cap beam. The following works are in progress: Construction of inner parapet walls at the square. Backfilling-compaction works. PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL The following works are in progress: Demolition of concrete at surface level. Polyurethane injections at the connecting tunnel and the shaft. Disassembly of building crane. Installation of balustrades at the staircase. Excavation works on Deligianni Street for the connection of the shaft with the sewage network.<\/p>\n","protected":false},"author":8,"featured_media":23517,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-23518","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-scaled.jpg",2560,1440,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-scaled.jpg",2560,1440,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-scaled.jpg",2560,1440,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-300x169.jpg",300,169,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-1024x576.jpg",960,540,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-1536x864.jpg",1536,864,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-2048x1152.jpg",2048,1152,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-1140x641.jpg",1140,641,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2022\/06\/AM_Maniatika_Project-Progress_May-2022a-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"ivassalos","author_link":"https:\/\/www.emetro.gr\/?author=8"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"TZAVELA Shaft The following works have been completed: Architectural finishes \u2013 Painting works at the staircase (walls, floors). Construction of sound absorbing plaster. Installation of staircase balustrades and balustrades at the street-level staircase. Installation of the entrance hatch at street level. Reinstatement of Tzavela and Lakonias Streets, opening to the MANIATIKA STATION STATION\u2019s OPEN CUT&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/23518","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/8"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=23518"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/23518\/revisions"}],"predecessor-version":[{"id":23519,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/23518\/revisions\/23519"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/23517"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=23518"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=23518"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=23518"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}