{"id":22141,"date":"2021-12-15T14:01:16","date_gmt":"2021-12-15T11:01:16","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=22141"},"modified":"2024-06-21T11:38:25","modified_gmt":"2024-06-21T08:38:25","slug":"november-2021","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=22141&lang=en","title":{"rendered":"NOVEMBER 2021"},"content":{"rendered":"<p><strong><u>TZAVELA Shaft<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Permanent lining of the shaft and of the connecting tunnel.<\/li>\n<li>Construction of sound absorbing plaster.<\/li>\n<li>Installation of staircase balustrades.<\/li>\n<li>Reinstatement of Tzavela and Lakonias Streets, opening to the<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Architectural finishes \u2013 staircase painting works.<\/li>\n<\/ul>\n<p><strong><u>MANIATIKA STATION<\/u><\/strong><\/p>\n<p><strong><u>STATION\u2019s OPEN CUT <\/u><\/strong><strong>\u00a0\u00a0\u00a0\u00a0\u00a0<\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Permanent lining of the shaft.<\/li>\n<li>Construction of partition walls at the station\u2019s expropriation limits (street level).<\/li>\n<li>Surface reinstatement (construction of sidewalk) at Mavromichali street.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Architectural finishes \u2013 Painting works at levels -4, -3, -2, -1.<\/li>\n<li>Installation of metal structures in room 3.12.<\/li>\n<li>Installation of steel supports of false ceilings and steel cladding (panels) on the walls of the main areas at the station\u2019s level -1.<\/li>\n<li>Construction of partition walls for flower beds (street level) at the station.<\/li>\n<\/ul>\n<p><strong><u>MAIN TUNNEL OF THE STATION (<\/u><\/strong><strong><u>\u039d\u0391\u03a4\u039c<\/u><\/strong><strong><u>)<\/u><\/strong><\/p>\n<p><strong>\u00a0<\/strong><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Steel cladding on the roof and side coverings.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>There are no works in progress.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND NATM SECTIONS OF THE STATION (NATM)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Installation of granites at the platforms.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of steel panels at the access tunnels of the station and at the upper transverse access gallery.<\/li>\n<\/ul>\n<p><strong><u>SOUTH VENTILATION SHAFT OF THE STATION <\/u><\/strong>(Koumoundourou Street)<\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Permanent lining of the shaft and of the connecting tunnel.<\/li>\n<li>Construction of perimeter wall at the boundaries of the expropriation.<\/li>\n<li>Construction of metal structures at K.P. +8.36 and +21.00.<\/li>\n<li>Application of sound absorbing plaster.<\/li>\n<li>Installation of staircase balustrades.<\/li>\n<li>Architectural finishes (painting works).<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Surface reinstatement (construction of sidewalk and of surrounding area).<\/li>\n<\/ul>\n<p><strong><u>NORTH VENTILATION SHAFT OF THE STATION <\/u><\/strong>(Dimitrakopoulou Street)<\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Permanent lining of the shaft and of the connecting tunnel.<\/li>\n<li>Pile cap beam demolition.<\/li>\n<li>Installation of metal structures at K.P. +8.08 and +24.98.<\/li>\n<li>Construction of sound absorbing plaster.<\/li>\n<li>Architectural finishes (painting works).<\/li>\n<li>Installation of staircase balustrades.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>There are no works in progress.<\/li>\n<\/ul>\n<p><strong><u>MELA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of intermediate slabs (landings).<\/li>\n<li>Concreting of interior wall.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Scrubbing and painting works at the staircase.<\/li>\n<li>Placing of sound absorbing plaster.<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS<\/u><\/strong><strong><u> STATION<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of main station (works at a small section of the roof slab are pending).<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Excavation and temporary retaining of entrances 2 &amp; 3, as well as of access 3 lift shaft.<\/li>\n<li>Construction of architectural finishes (installation of metal doors at levels -2 and -3, installation of granites at the west platform and at level -1, installation of handrails at the staircases intended for personnel, painting works at level -1, wall cladding at track level, installation of other metal and special structures).<\/li>\n<li>Installation of mechanical equipment at levels -1, -2 and at the level underneath the platforms.<\/li>\n<li>High pressure water blasting at the diaphragm walls between the station and accesses 2 &amp; 3.<\/li>\n<li>Waterproofing of accesses 1, 2 &amp; 3.<\/li>\n<li>Concreting of foundation slab at accesses 2 &amp; 3.<\/li>\n<li>Concreting of exterior perimeter partition walls at accesses 1, 2 &amp; 3.<\/li>\n<\/ul>\n<p><strong><u>ROLOI SHAFT &amp; NATM ACCESS TUNNEL<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Polyurethane injections.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO STATION <\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE <\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 <\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<li>Traffic reinstatement at V. Georgiou Street.<\/li>\n<li>Traffic reinstatement at Karaiskou street.<\/li>\n<\/ul>\n<p><strong>The following works are in progress<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Backfilling \u2013 compaction works at street level.<\/li>\n<li>Reinstatement at street level (paving works at Karaiskou street and construction inner parapet walls at the square).<\/li>\n<li>Installation of wall panels at level -1.<\/li>\n<li>Construction of false ceiling at the concourse level.<\/li>\n<li>Preparatory painting works in personnel areas at the concourse level.<\/li>\n<li>Installation of wall panels at the platform level.<\/li>\n<li>Construction of wall-mounted granites at the platform level.<\/li>\n<li>Installation of floor granite at the platform level and at the concourse level.<\/li>\n<li>Construction of balustrades at staircases 7 and 8.<\/li>\n<li>Conservation of the Project\u2019s archaeological finds.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND SECTION OF THE STATION <\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining.<\/li>\n<\/ul>\n<p><strong>\u00a0 <\/strong><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of steel panels at the platform level.<\/li>\n<\/ul>\n<p><strong><u>STAIRCASE GALLERIES<\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining and secondary concrete.<\/li>\n<\/ul>\n<p><strong><u>KORAI SQUARE ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, secondary concrete.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of wall<\/li>\n<\/ul>\n<p><strong><u>BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of permanent lining.<strong>\u00a0 \u00a0\u00a0<\/strong><\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Transfer of the antiquities in the floor recess displaying the pebble floor.<\/li>\n<li>Installation of wall granites.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO VENTILATION SHAFT<\/u><\/strong><strong><u> (<\/u><\/strong><strong><u>RALLIOS SHAFT) AND VENTILATION GALLERY<\/u><\/strong><strong>\u00a0 \u00a0 \u00a0\u00a0<\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<li>Sidewalk reinstatement on V. Georgiou Street.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of metal staircase.<\/li>\n<\/ul>\n<p><strong><u>TRIPLE TRACK NATM TUNNEL<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Construction of permanent lining.<\/li>\n<\/ul>\n<p><strong><u>DELIGIANNI SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Excavation and temporary retaining.<\/li>\n<li>Concreting of the permanent lining.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Closing of slab openings (due to pumping station).<\/li>\n<li>Roof waterproofing.<\/li>\n<\/ul>\n<p><strong><u>PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining of the connecting tunnel.<\/li>\n<li>Concreting of the shaft\u2019s perimeter walls up to +21.3.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Construction of intermediate wall (up to +21.0) and staircase (up to +16.0).<\/li>\n<\/ul>\n","protected":false},"excerpt":{"rendered":"<p>TZAVELA Shaft The following works have been completed: Permanent lining of the shaft and of the connecting tunnel. Construction of sound absorbing plaster. Installation of staircase balustrades. Reinstatement of Tzavela and Lakonias Streets, opening to the The following works are in progress: Architectural finishes \u2013 staircase painting works. MANIATIKA STATION STATION\u2019s OPEN CUT \u00a0\u00a0\u00a0\u00a0\u00a0 The following works have been completed: Permanent lining of the shaft. Construction of partition walls at the station\u2019s expropriation limits (street level). Surface reinstatement (construction of sidewalk) at Mavromichali street. The following works are in progress: Architectural finishes \u2013 Painting works at levels -4, -3, -2, -1. Installation of metal structures in room 3.12. Installation of steel supports of false ceilings and steel cladding (panels) on the walls of the main areas at the station\u2019s level -1. Construction of partition walls for flower beds (street level) at the station. MAIN TUNNEL OF THE STATION (\u039d\u0391\u03a4\u039c) \u00a0The following works have been completed: Steel cladding on the roof and side coverings. The following works are in progress: There are no works in progress. UNDERGROUND NATM SECTIONS OF THE STATION (NATM) The following works have been completed: Installation of granites at the platforms. The following works are in progress: Installation of steel panels at the access tunnels of the station and at the upper transverse access gallery. SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street) The following works have been completed: Permanent lining of the shaft and of the connecting tunnel. Construction of perimeter wall at the boundaries of the expropriation. Construction of metal structures at K.P. +8.36 and +21.00. Application of sound absorbing plaster. Installation of staircase balustrades. Architectural finishes (painting works). The following works are in progress: Surface reinstatement (construction of sidewalk and of surrounding area). NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street) The following works have been completed: Permanent lining of the shaft and of the connecting tunnel. Pile cap beam demolition. Installation of metal structures at K.P. +8.08 and +24.98. Construction of sound absorbing plaster. Architectural finishes (painting works). Installation of staircase balustrades. The following works are in progress: There are no works in progress. MELA SHAFT The following works have been completed: Concreting of intermediate slabs (landings). Concreting of interior wall. The following works are in progress: Scrubbing and painting works at the staircase. Placing of sound absorbing plaster. PIRAEUS STATION The following works have been completed: Concreting of main station (works at a small section of the roof slab are pending). The following works are in progress: Excavation and temporary retaining of entrances 2 &amp; 3, as well as of access 3 lift shaft. Construction of architectural finishes (installation of metal doors at levels -2 and -3, installation of granites at the west platform and at level -1, installation of handrails at the staircases intended for personnel, painting works at level -1, wall cladding at track level, installation of other metal and special structures). Installation of mechanical equipment at levels -1, -2 and at the level underneath the platforms. High pressure water blasting at the diaphragm walls between the station and accesses 2 &amp; 3. Waterproofing of accesses 1, 2 &amp; 3. Concreting of foundation slab at accesses 2 &amp; 3. Concreting of exterior perimeter partition walls at accesses 1, 2 &amp; 3. ROLOI SHAFT &amp; NATM ACCESS TUNNEL The following works have been completed: Sealing of the temporary pumping station. The following works are in progress: Polyurethane injections. DIMOTIKO THEATRO STATION MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE The following works have been completed:\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 Sealing of the temporary pumping station. Traffic reinstatement at V. Georgiou Street. Traffic reinstatement at Karaiskou street. The following works are in progress: Backfilling \u2013 compaction works at street level. Reinstatement at street level (paving works at Karaiskou street and construction inner parapet walls at the square). Installation of wall panels at level -1. Construction of false ceiling at the concourse level. Preparatory painting works in personnel areas at the concourse level. Installation of wall panels at the platform level. Construction of wall-mounted granites at the platform level. Installation of floor granite at the platform level and at the concourse level. Construction of balustrades at staircases 7 and 8. Conservation of the Project\u2019s archaeological finds. UNDERGROUND SECTION OF THE STATION The following works have been completed: Concreting of the permanent lining. \u00a0 The following works are in progress: Installation of steel panels at the platform level. STAIRCASE GALLERIES The following works have been completed: Concreting of the permanent lining and secondary concrete. KORAI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Concreting of the permanent lining, secondary concrete. The following works are in progress: Installation of wall BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Concreting of permanent lining.\u00a0 \u00a0\u00a0 The following works are in progress: Transfer of the antiquities in the floor recess displaying the pebble floor. Installation of wall granites. DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY\u00a0 \u00a0 \u00a0\u00a0 The following works have been completed: Sealing of the temporary pumping station. Sidewalk reinstatement on V. Georgiou Street. The following works are in progress: Installation of metal staircase. TRIPLE TRACK NATM TUNNEL The following works have been completed: Construction of permanent lining. DELIGIANNI SHAFT The following works have been completed: Excavation and temporary retaining. Concreting of the permanent lining. The following works are in progress: Closing of slab openings (due to pumping station). Roof waterproofing. PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL The following works have been completed: Concreting of the permanent lining of the connecting tunnel. Concreting of the shaft\u2019s perimeter walls up to +21.3. The following works are in progress: Construction of intermediate wall (up to +21.0) and staircase (up to +16.0).<\/p>\n","protected":false},"author":8,"featured_media":22105,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-22141","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-scaled.jpg",2560,1440,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-scaled.jpg",2560,1440,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-scaled.jpg",2560,1440,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-300x169.jpg",300,169,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-1024x576.jpg",960,540,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-1536x864.jpg",1536,864,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-2048x1152.jpg",2048,1152,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-1140x641.jpg",1140,641,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/12\/AM_Frear-Deligianni_progress_Noe-2021-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"ivassalos","author_link":"https:\/\/www.emetro.gr\/?author=8"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"TZAVELA Shaft The following works have been completed: Permanent lining of the shaft and of the connecting tunnel. Construction of sound absorbing plaster. Installation of staircase balustrades. Reinstatement of Tzavela and Lakonias Streets, opening to the The following works are in progress: Architectural finishes \u2013 staircase painting works. MANIATIKA STATION STATION\u2019s OPEN CUT \u00a0\u00a0\u00a0\u00a0\u00a0 The&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/22141","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/8"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=22141"}],"version-history":[{"count":2,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/22141\/revisions"}],"predecessor-version":[{"id":22143,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/22141\/revisions\/22143"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/22105"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=22141"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=22141"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=22141"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}