{"id":21475,"date":"2021-11-17T12:32:17","date_gmt":"2021-11-17T09:32:17","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=21475"},"modified":"2024-06-25T11:22:33","modified_gmt":"2024-06-25T08:22:33","slug":"21475","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=21475&lang=en","title":{"rendered":"September 2021"},"content":{"rendered":"<p>&nbsp;<\/p>\n<p>The equipment of the Platform Screen Doors has been delivered in all stations.<br \/>\n<strong>\u2022 Kritis Shaft:<\/strong> Preliminary works for the industrial flooring are in progress.<br \/>\n<strong>\u2022 NOMARCHIA Station (Station and Crossover):<\/strong> Works for the construction of granite water discharge grooves at the central staircase are in progress. At the crossover works for the backfilling of the ceiling slab in the area of the opening are in progress, along with preliminary reinstatement works at street-level and masonry works.<br \/>\n<strong>\u2022 KALAMARIA Station:<\/strong> Works for the implementation of the 10th traffic arrangement have been completed, while works at the fire fighting system are in progress.<br \/>\n<strong>\u2022 ARETSOU Shaft:<\/strong> Works for the installation of equipment for the traction power supply system are in progress.<br \/>\n<strong>\u2022 MICRA Station:<\/strong> Works for the installation of ceramic tiles, works for the installation of stainless steel balustrades and works for the installation of electrical trays are in progress.<br \/>\n<strong>TRACKWORK<\/strong><br \/>\nIn progress are works for the installation of the ventilation system and for the installation of electrical trays at the 1st interstation\/ track 2, works for the installation of electrical trays and cabling for the lighting system at the 2nd interstation\/ track 2, works for the installation of electrical trays at the 3rd interstation\/ track 1 and works for the installation of fire fighting hose cabinets at the 4th interstation\/ tracks 1 &amp; 2. In progress are also works for the installation of the 3rd rail at the tunnel section extending from ARETSOU Station up to the Forestation\/ tracks 1 and 2.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>&nbsp; The equipment of the Platform Screen Doors has been delivered in all stations. \u2022 Kritis Shaft: Preliminary works for the industrial flooring are in progress. \u2022 NOMARCHIA Station (Station and Crossover): Works for the construction of granite water discharge grooves at the central staircase are in progress. At the crossover works for the backfilling of the ceiling slab in the area of the opening are in progress, along with preliminary reinstatement works at street-level and masonry works. \u2022 KALAMARIA Station: Works for the implementation of the 10th traffic arrangement have been completed, while works at the fire fighting system are in progress. \u2022 ARETSOU Shaft: Works for the installation of equipment for the traction power supply system are in progress. \u2022 MICRA Station: Works for the installation of ceramic tiles, works for the installation of stainless steel balustrades and works for the installation of electrical trays are in progress. TRACKWORK In progress are works for the installation of the ventilation system and for the installation of electrical trays at the 1st interstation\/ track 2, works for the installation of electrical trays and cabling for the lighting system at the 2nd interstation\/ track 2, works for the installation of electrical trays at the 3rd interstation\/ track 1 and works for the installation of fire fighting hose cabinets at the 4th interstation\/ tracks 1 &amp; 2. In progress are also works for the installation of the 3rd rail at the tunnel section extending from ARETSOU Station up to the Forestation\/ tracks 1 and 2.<\/p>\n","protected":false},"author":4,"featured_media":21073,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[544],"tags":[],"class_list":["post-21475","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-kalamaria-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21.jpg",1600,1200,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21.jpg",1600,1200,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21.jpg",1600,1200,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21-300x225.jpg",300,225,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21-1024x768.jpg",960,720,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21-1536x1152.jpg",1536,1152,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21.jpg",1600,1200,false],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21-1140x855.jpg",1140,855,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/10\/KALAMARIA_09_21-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"psymeonidou","author_link":"https:\/\/www.emetro.gr\/?author=4"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=544&#038;lang=en\" rel=\"category\">Kalamaria Project progress<\/a>","rttpg_excerpt":"&nbsp; The equipment of the Platform Screen Doors has been delivered in all stations. \u2022 Kritis Shaft: Preliminary works for the industrial flooring are in progress. \u2022 NOMARCHIA Station (Station and Crossover): Works for the construction of granite water discharge grooves at the central staircase are in progress. At the crossover works for the backfilling&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/21475","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/4"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=21475"}],"version-history":[{"count":2,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/21475\/revisions"}],"predecessor-version":[{"id":21481,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/21475\/revisions\/21481"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/21073"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=21475"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=21475"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=21475"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}