{"id":21097,"date":"2021-06-15T16:10:52","date_gmt":"2021-06-15T13:10:52","guid":{"rendered":"https:\/\/www.emetro.gr?p=21097"},"modified":"2024-06-21T12:16:02","modified_gmt":"2024-06-21T09:16:02","slug":"may-2021-3","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=21097&lang=en","title":{"rendered":"MAY 2021"},"content":{"rendered":"<p><strong><u>TZAVELLA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<\/li>\n<li>Construction of sound absorbing plaster.<\/li>\n<\/ul>\n<p><strong><u>MANIATIKA STATION<\/u><\/strong><\/p>\n<p><strong><u>STATION\u2019s OPEN CUT\u00a0<\/u><\/strong><strong>\u00a0\u00a0\u00a0\u00a0\u00a0<\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Waterproofing of the roof slab.<\/li>\n<li>Construction of shaft No. 4 at street level.<\/li>\n<li>Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1.<\/li>\n<li>Architectural finishes \u2013 Painting works at levels -4, -3, -2, -1.<\/li>\n<li>Industrial flooring at levels -4, -3, -2, -1.<\/li>\n<li>Installation of ceramic tiles and granites at levels -4, -3, -2, -1.<\/li>\n<li>Installation of metal structures in room 3.12.<\/li>\n<li>Installation of doors.<\/li>\n<li>Installation of ventilation grids.<\/li>\n<li>Station backfilling.<\/li>\n<\/ul>\n<p><strong><u>MAIN TUNNEL OF THE STATION (<\/u><\/strong><strong><u>\u039d\u0391\u03a4\u039c<\/u><\/strong><strong><u>)<\/u><\/strong><\/p>\n<p><strong>\u00a0<\/strong><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the station\u2019s main tunnel.<\/li>\n<li>Secondary concreting in platforms.<\/li>\n<li>Installation of granites in platforms.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of false ceilings and side-covering panels.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND NATM SECTIONS OF THE STATION (NATM)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the construction of the permanent lining.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of granites at the entrances of the staircases and at the cross-over tunnel.<\/li>\n<li>Installation of items supporting the platforms\u2019 metal lining at the upper transverse access tunnel.<\/li>\n<\/ul>\n<p><strong><u>SOUTH VENTILATION SHAFT OF THE STATION\u00a0<\/u><\/strong>(Koumoundourou Street)<\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<\/li>\n<li>Masonry walls \u2013 plastering works.<\/li>\n<li>Construction of perimeter wall at the boundaries of the expropriation.<\/li>\n<li>Construction of metal structures at K.P. +8.36 and +21.00.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Secondary staircase concreting works.<\/li>\n<li>Architectural finishes (painting works).<\/li>\n<\/ul>\n<p><strong><u>NORTH VENTILATION SHAFT OF THE STATION\u00a0<\/u><\/strong>(Dimitrakopoulou Street)<\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<\/li>\n<li>Pile cap beam demolition.<\/li>\n<li>Installation of metal structures at K.P. +8.08 and +24.98.<\/li>\n<li>Construction of sound absorbing plaster.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Architectural finishes (painting works).<\/li>\n<\/ul>\n<p><strong><u>MELA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of the final lining of the NATM tunnel (vault + reverse arch).<\/li>\n<li>Concreting of the pumping station roof<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of reinforcement and concreting of the perimeter walls of the permanent lining.<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS STATION<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of main station.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Excavation and temporary retaining of entrances 1, 2 &amp; 3.<\/li>\n<li>Construction of architectural finishes (masonry walls, plastering at level -1, painting works at levels -1 and -3, industrial flooring, floor filling, floor screed concrete works, installation of ceramic tiles at level -1, metal doors at levels -2 and -3, filling laying works at levels -1 and -2, false-ceilings), area configuration works at ticketing level -1).<\/li>\n<li>Laying of electrical insulation sheets at platform level.<\/li>\n<li>Hydro-demolition of diaphragm walls between the station and the accesses 3.<\/li>\n<\/ul>\n<p><strong><u>ROLOI SHAFT &amp; NATM ACCESS TUNNEL<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Reinstatement works at street level.<\/li>\n<li>Water proofing works at the roof of the shaft<\/li>\n<li>Laying of industrial flooring.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO STATION<\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE<\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0<\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station<\/li>\n<\/ul>\n<p><strong>The following works are in progress<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Backfilling \u2013 compaction works<\/li>\n<li>Installation of doors at the platform the E\/M levels<\/li>\n<li>Installation of floor granite at the ticketing level and at the staircases<\/li>\n<li>Conservation of the Project\u2019s archaeological finds.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND SECTION OF THE STATION<\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of floor granite.<\/li>\n<\/ul>\n<p><strong><u>STAIRCASE GALLERIES<\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining and secondary concrete.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of floor granite at the staircases.<\/li>\n<\/ul>\n<p><strong><u>KORAI SQUARE ENTRANCE AND ACCESS GALLERY<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, secondary concrete..<\/li>\n<\/ul>\n<p><strong><u>BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining<strong>\u00a0 \u00a0\u00a0<\/strong><\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of floor granite at the connecting tunnel<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO VENTILATION SHAFT (<\/u><\/strong><strong><u>RALLIOS SHAFT) AND VENTILATION GALLERY<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Reinstatement at street level<\/li>\n<\/ul>\n<p><strong><u>TRIPLE TRACK NATM TUNNEL<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Construction of permanent lining<\/li>\n<\/ul>\n<p><strong><u>DELIGIANNI SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Excavation and temporary retaining<\/li>\n<li>Waterproofing, construction of foundation slab and perimeter walls down to -3.0.<\/li>\n<\/ul>\n<p><strong><u>PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining of the connecting tunnel.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Concreting of permanent lining of the shaft\u2019s perimeter walls (completed up to +4.5)<\/li>\n<\/ul>\n","protected":false},"excerpt":{"rendered":"<p>TZAVELLA SHAFT The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Construction of sound absorbing plaster. MANIATIKA STATION STATION\u2019s OPEN CUT\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 The following works have been completed: Completion of the permanent lining of the shaft. The following works are in progress: Waterproofing of the roof slab. Construction of shaft No. 4 at street level. Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1. Architectural finishes \u2013 Painting works at levels -4, -3, -2, -1. Industrial flooring at levels -4, -3, -2, -1. Installation of ceramic tiles and granites at levels -4, -3, -2, -1. Installation of metal structures in room 3.12. Installation of doors. Installation of ventilation grids. Station backfilling. MAIN TUNNEL OF THE STATION (\u039d\u0391\u03a4\u039c) \u00a0The following works have been completed: Completion of the permanent lining of the station\u2019s main tunnel. Secondary concreting in platforms. Installation of granites in platforms. The following works are in progress: Installation of false ceilings and side-covering panels. UNDERGROUND NATM SECTIONS OF THE STATION (NATM) The following works have been completed: Completion of the construction of the permanent lining. The following works are in progress: Installation of granites at the entrances of the staircases and at the cross-over tunnel. Installation of items supporting the platforms\u2019 metal lining at the upper transverse access tunnel. SOUTH VENTILATION SHAFT OF THE STATION\u00a0(Koumoundourou Street) The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Masonry walls \u2013 plastering works. Construction of perimeter wall at the boundaries of the expropriation. Construction of metal structures at K.P. +8.36 and +21.00. The following works are in progress: Secondary staircase concreting works. Architectural finishes (painting works). NORTH VENTILATION SHAFT OF THE STATION\u00a0(Dimitrakopoulou Street) The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Pile cap beam demolition. Installation of metal structures at K.P. +8.08 and +24.98. Construction of sound absorbing plaster. The following works are in progress: Architectural finishes (painting works). MELA SHAFT The following works have been completed: Concreting of the final lining of the NATM tunnel (vault + reverse arch). Concreting of the pumping station roof The following works are in progress: Installation of reinforcement and concreting of the perimeter walls of the permanent lining. PIRAEUS STATION The following works have been completed: Concreting of main station. The following works are in progress: Excavation and temporary retaining of entrances 1, 2 &amp; 3. Construction of architectural finishes (masonry walls, plastering at level -1, painting works at levels -1 and -3, industrial flooring, floor filling, floor screed concrete works, installation of ceramic tiles at level -1, metal doors at levels -2 and -3, filling laying works at levels -1 and -2, false-ceilings), area configuration works at ticketing level -1). Laying of electrical insulation sheets at platform level. Hydro-demolition of diaphragm walls between the station and the accesses 3. ROLOI SHAFT &amp; NATM ACCESS TUNNEL The following works have been completed: Sealing of the temporary pumping station. The following works are in progress: Reinstatement works at street level. Water proofing works at the roof of the shaft Laying of industrial flooring. DIMOTIKO THEATRO STATION MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE The following works have been completed:\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 Sealing of the temporary pumping station The following works are in progress: Backfilling \u2013 compaction works Installation of doors at the platform the E\/M levels Installation of floor granite at the ticketing level and at the staircases Conservation of the Project\u2019s archaeological finds. UNDERGROUND SECTION OF THE STATION The following works have been completed: Concreting of the permanent lining The following works are in progress: Installation of floor granite. STAIRCASE GALLERIES The following works have been completed: Concreting of the permanent lining and secondary concrete. The following works are in progress: Installation of floor granite at the staircases. KORAI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Concreting of the permanent lining, secondary concrete.. BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Concreting of the permanent lining\u00a0 \u00a0\u00a0 The following works are in progress: Installation of floor granite at the connecting tunnel DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY The following works have been completed: Sealing of the temporary pumping station The following works are in progress: Reinstatement at street level TRIPLE TRACK NATM TUNNEL The following works have been completed: Construction of permanent lining DELIGIANNI SHAFT The following works have been completed: Excavation and temporary retaining Waterproofing, construction of foundation slab and perimeter walls down to -3.0. PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL The following works have been completed: Concreting of the permanent lining of the connecting tunnel. The following works are in progress: Concreting of permanent lining of the shaft\u2019s perimeter walls (completed up to +4.5)<\/p>\n","protected":false},"author":8,"featured_media":21098,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-21097","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1.jpg",2560,1707,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1.jpg",2560,1707,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1.jpg",2560,1707,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1-300x200.jpg",300,200,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1-1024x683.jpg",960,640,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1-1536x1024.jpg",1536,1024,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1-2048x1366.jpg",2048,1366,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1-1140x760.jpg",1140,760,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/06\/AM_Peiraias_progress_May-2021-scaled-1-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"ivassalos","author_link":"https:\/\/www.emetro.gr\/?author=8"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"TZAVELLA SHAFT The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Construction of sound absorbing plaster. MANIATIKA STATION STATION\u2019s OPEN CUT\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 The following works have been completed: Completion of the permanent lining of the shaft. The following works are in progress: Waterproofing of the roof&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/21097","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/8"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=21097"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/21097\/revisions"}],"predecessor-version":[{"id":21099,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/21097\/revisions\/21099"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/21098"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=21097"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=21097"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=21097"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}