{"id":20962,"date":"2021-09-10T15:36:41","date_gmt":"2021-09-10T12:36:41","guid":{"rendered":"https:\/\/www.emetro.gr?p=20962"},"modified":"2024-06-21T12:11:37","modified_gmt":"2024-06-21T09:11:37","slug":"august-2021","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=20962&lang=en","title":{"rendered":"AUGUST 2021"},"content":{"rendered":"<p><strong><u>TZAVELA Shaft<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<\/li>\n<li>Construction of sound absorbing plaster.<\/li>\n<li>Traffic Arrangement \u2013 Phase B\u2019<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Reinstatement works at Tzavela and Lakonias Streets (installation of curbs, construction of gutters, sidewalk paving activities, installation of sumps, construction of rain water network).<\/li>\n<\/ul>\n<p><strong><u>MANIATIKA STATION<\/u><\/strong><\/p>\n<p><strong><u>STATION\u2019s OPEN CUT\u00a0<\/u><\/strong><strong>\u00a0\u00a0\u00a0\u00a0\u00a0<\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Waterproofing of the roof slab.<\/li>\n<li>Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1.<\/li>\n<li>Architectural finishes \u2013 Painting works at levels -4, -3, -2, -1.<\/li>\n<li>Industrial flooring at levels -4, -3, -2, -1.<\/li>\n<li>Installation of ceramic tiles and granites at levels -4, -3, -2, -1.<\/li>\n<li>Installation of metal structures in room 3.12.<\/li>\n<li>Installation of doors.<\/li>\n<li>Installation of ventilation grids.<\/li>\n<li>Installation of false-ceilings\u2019 supports in room 1.4.<\/li>\n<li>Station backfilling.<\/li>\n<li>Demolition of pile cap beam.<\/li>\n<\/ul>\n<p><strong><u>MAIN TUNNEL OF THE STATION (<\/u><\/strong><strong><u>\u039d\u0391\u03a4\u039c<\/u><\/strong><strong><u>)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the station\u2019s main tunnel.<\/li>\n<li>Secondary concreting in platforms.<\/li>\n<li>Installation of granites in platforms.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of false ceilings and side-covering panels.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND NATM SECTIONS OF THE STATION (NATM)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of granites at the entrances of the staircases and at the cross-over tunnel.<\/li>\n<li>Installation of items supporting metal lining at the platforms, at the station\u2019s access galleries and at the upper transverse access tunnel.<\/li>\n<li>Installation of consolidated emergency units.<\/li>\n<\/ul>\n<p><strong><u>SOUTH VENTILATION SHAFT OF THE STATION\u00a0<\/u><\/strong>(Koumoundourou Street)<\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<\/li>\n<li>Masonry walls \u2013 plastering works.<\/li>\n<li>Construction of perimeter wall at the boundaries of the expropriation.<\/li>\n<li>Construction of metal structures at K.P. +8.36 and +21.00.<\/li>\n<li>Staircase secondary concreting works.<\/li>\n<\/ul>\n<p><strong><u>NORTH VENTILATION SHAFT OF THE STATION\u00a0<\/u><\/strong>(Dimitrakopoulou Street)<\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<\/li>\n<li>Pile cap beam demolition.<\/li>\n<li>Installation of metal structures at K.P. +8.08 and +24.98.<\/li>\n<li>Construction of sound absorbing plaster.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Architectural finishes (painting works).<\/li>\n<\/ul>\n<p><strong><u>MELA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of the pumping station roof<\/li>\n<li>Installation of reinforcement and concreting of perimeter walls.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of reinforcement and concreting of the shaft\u2019s staircase.<\/li>\n<li>Installation of reinforcement and concreting of the inner wall.<\/li>\n<li>Installation of reinforcement and concreting of the intermediate slabs (landing).<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS<\/u><\/strong><strong><u>\u00a0STATION<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of main station.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Excavation and temporary retaining of entrances 1 &amp; 2.<\/li>\n<li>Construction of architectural finishes (painting works at levels -1 and -2 and installation of metal doors at levels -1, -2 and -3).<\/li>\n<li>Installation of mechanical equipment at levels -1, -2 and at the level underneath the platforms.<\/li>\n<li>Hydro-demolition of diaphragm walls between the station and the accesses.<\/li>\n<\/ul>\n<p><strong><u>ROLOI SHAFT &amp; NATM ACCESS TUNNEL<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Painting works of the shaft.<\/li>\n<li>Reinstatement at street level.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO STATION<\/u><\/strong><\/p>\n<p><strong>\u00a0<\/strong><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE<\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0<\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station<\/li>\n<\/ul>\n<p><strong>The following works are in progress<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Construction of routing of E\/M networks at street level<\/li>\n<li>Reinstatement at street level (flooring works using porphyry (V. Georgiou Street).<\/li>\n<li>Installation of floor granite at the platform level<\/li>\n<li>Conservation of the Project\u2019s archaeological finds.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND SECTION OF THE STATION<\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining<\/li>\n<\/ul>\n<p><strong><u>STAIRCASE GALLERIES<\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining and secondary concrete.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of floor granite at the staircases.<\/li>\n<\/ul>\n<p><strong><u>KORAI SQUARE<\/u><\/strong><strong><u>\u00a0ENTRANCE AND ACCESS GALLERY<\/u><\/strong><\/p>\n<p><strong>\u00a0<\/strong><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, secondary concrete.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Installation of wall<\/li>\n<\/ul>\n<p><strong><u>BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining<strong>\u00a0 \u00a0<\/strong><\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Reinstatement at street level<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO VENTILATION SHAFT<\/u><\/strong><strong><u>\u00a0(<\/u><\/strong><strong><u>RALLIOS SHAFT) AND VENTILATION GALLERY<\/u><\/strong><strong>\u00a0 \u00a0\u00a0<\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station<\/li>\n<li>Painting works<\/li>\n<\/ul>\n<p><strong><u>TRIPLE TRACK NATM TUNNEL<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Construction of permanent lining<\/li>\n<\/ul>\n<p><strong><u>DELIGIANNI SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Excavation and temporary retaining<\/li>\n<li>Waterproofing, construction of foundation slab and perimeter walls up to +7.5<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Roof slab reinforcement activities (+8.5)<\/li>\n<\/ul>\n<p><strong><u>PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining of the connecting tunnel.<\/li>\n<li>Concreting of the shaft\u2019s perimeter wall up to +21.3.<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Construction of intermediate wall and staircase down to -5.8<\/li>\n<\/ul>\n","protected":false},"excerpt":{"rendered":"<p>TZAVELA Shaft The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Construction of sound absorbing plaster. Traffic Arrangement \u2013 Phase B\u2019 The following works are in progress: Reinstatement works at Tzavela and Lakonias Streets (installation of curbs, construction of gutters, sidewalk paving activities, installation of sumps, construction of rain water network). MANIATIKA STATION STATION\u2019s OPEN CUT\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 The following works have been completed: Completion of the permanent lining of the shaft. The following works are in progress: Waterproofing of the roof slab. Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1. Architectural finishes \u2013 Painting works at levels -4, -3, -2, -1. Industrial flooring at levels -4, -3, -2, -1. Installation of ceramic tiles and granites at levels -4, -3, -2, -1. Installation of metal structures in room 3.12. Installation of doors. Installation of ventilation grids. Installation of false-ceilings\u2019 supports in room 1.4. Station backfilling. Demolition of pile cap beam. MAIN TUNNEL OF THE STATION (\u039d\u0391\u03a4\u039c) The following works have been completed: Completion of the permanent lining of the station\u2019s main tunnel. Secondary concreting in platforms. Installation of granites in platforms. The following works are in progress: Installation of false ceilings and side-covering panels. UNDERGROUND NATM SECTIONS OF THE STATION (NATM) The following works have been completed: Completion of the permanent lining. The following works are in progress: Installation of granites at the entrances of the staircases and at the cross-over tunnel. Installation of items supporting metal lining at the platforms, at the station\u2019s access galleries and at the upper transverse access tunnel. Installation of consolidated emergency units. SOUTH VENTILATION SHAFT OF THE STATION\u00a0(Koumoundourou Street) The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Masonry walls \u2013 plastering works. Construction of perimeter wall at the boundaries of the expropriation. Construction of metal structures at K.P. +8.36 and +21.00. Staircase secondary concreting works. NORTH VENTILATION SHAFT OF THE STATION\u00a0(Dimitrakopoulou Street) The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Pile cap beam demolition. Installation of metal structures at K.P. +8.08 and +24.98. Construction of sound absorbing plaster. The following works are in progress: Architectural finishes (painting works). MELA SHAFT The following works have been completed: Concreting of the pumping station roof Installation of reinforcement and concreting of perimeter walls. \u00a0The following works are in progress: Installation of reinforcement and concreting of the shaft\u2019s staircase. Installation of reinforcement and concreting of the inner wall. Installation of reinforcement and concreting of the intermediate slabs (landing). PIRAEUS\u00a0STATION The following works have been completed: Concreting of main station. The following works are in progress: Excavation and temporary retaining of entrances 1 &amp; 2. Construction of architectural finishes (painting works at levels -1 and -2 and installation of metal doors at levels -1, -2 and -3). Installation of mechanical equipment at levels -1, -2 and at the level underneath the platforms. Hydro-demolition of diaphragm walls between the station and the accesses. ROLOI SHAFT &amp; NATM ACCESS TUNNEL The following works have been completed: Sealing of the temporary pumping station. The following works are in progress: Painting works of the shaft. Reinstatement at street level. DIMOTIKO THEATRO STATION \u00a0MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE The following works have been completed:\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0\u00a0 Sealing of the temporary pumping station The following works are in progress: Construction of routing of E\/M networks at street level Reinstatement at street level (flooring works using porphyry (V. Georgiou Street). Installation of floor granite at the platform level Conservation of the Project\u2019s archaeological finds. UNDERGROUND SECTION OF THE STATION The following works have been completed: Concreting of the permanent lining STAIRCASE GALLERIES The following works have been completed: Concreting of the permanent lining and secondary concrete. The following works are in progress: Installation of floor granite at the staircases. KORAI SQUARE\u00a0ENTRANCE AND ACCESS GALLERY \u00a0The following works have been completed: Concreting of the permanent lining, secondary concrete. The following works are in progress: Installation of wall BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Concreting of the permanent lining\u00a0 \u00a0 The following works are in progress: Reinstatement at street level DIMOTIKO THEATRO VENTILATION SHAFT\u00a0(RALLIOS SHAFT) AND VENTILATION GALLERY\u00a0 \u00a0\u00a0 The following works have been completed: Sealing of the temporary pumping station Painting works TRIPLE TRACK NATM TUNNEL The following works have been completed: Construction of permanent lining DELIGIANNI SHAFT The following works have been completed: Excavation and temporary retaining Waterproofing, construction of foundation slab and perimeter walls up to +7.5 The following works are in progress: Roof slab reinforcement activities (+8.5) PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL The following works have been completed: Concreting of the permanent lining of the connecting tunnel. Concreting of the shaft\u2019s perimeter wall up to +21.3. The following works are in progress: Construction of intermediate wall and staircase down to -5.8<\/p>\n","protected":false},"author":8,"featured_media":20838,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-20962","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1.jpg",2560,1440,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1.jpg",2560,1440,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1.jpg",2560,1440,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1-300x169.jpg",300,169,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1-1024x576.jpg",960,540,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1-1536x864.jpg",1536,864,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1-2048x1152.jpg",2048,1152,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1-1140x641.jpg",1140,641,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/09\/AM_Frear-Tzavela_progress_July-2021-scaled-1-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"ivassalos","author_link":"https:\/\/www.emetro.gr\/?author=8"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"TZAVELA Shaft The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Construction of sound absorbing plaster. Traffic Arrangement \u2013 Phase B\u2019 The following works are in progress: Reinstatement works at Tzavela and Lakonias Streets (installation of curbs, construction of gutters, sidewalk paving activities, installation of&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/20962","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/8"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=20962"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/20962\/revisions"}],"predecessor-version":[{"id":20963,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/20962\/revisions\/20963"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/20838"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=20962"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=20962"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=20962"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}