{"id":17789,"date":"2021-05-17T09:58:40","date_gmt":"2021-05-17T06:58:40","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=17789"},"modified":"2024-06-21T12:16:40","modified_gmt":"2024-06-21T09:16:40","slug":"april-2021","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=17789&lang=en","title":{"rendered":"APRIL 2021"},"content":{"rendered":"<p><strong><u>TZAVELA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<\/li>\n<\/ul>\n<p><strong><u>MANIATIKA STATION <\/u><\/strong><\/p>\n<p><strong><u>STATION\u2019s OPEN CUT <\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Waterproofing of the roof slab.<\/li>\n<li>Construction of shafts 4 and 7 at street level.<\/li>\n<li>Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1.<\/li>\n<li>Architectural finishes \u2013 Painting works at levels -4, -3, -2, -1.<\/li>\n<li>Industrial flooring at levels -4, -3, -2, -1.<\/li>\n<li>Installation of ceramic tiles at levels -4, -3, -2, -1.<\/li>\n<li>Installation of metal structures in room 3.12.<\/li>\n<li>Installation of doors.<\/li>\n<\/ul>\n<p><strong><u>MAIN TUNNEL OF THE STATION<\/u><\/strong><strong><u> (<\/u><\/strong><strong><u>\u039d\u0391\u03a4\u039c<\/u><\/strong><strong><u>)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the station\u2019s main tunnel.<\/li>\n<li>Secondary concreting in platforms.<\/li>\n<li>Installation of granites in platforms.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of items supporting the platforms\u2019 metal lining.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND NATM SECTIONS OF THE STATION (NATM)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the construction of the permanent lining of the station\u2019s eastern lift.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of items supporting the platforms\u2019 metal lining.<\/li>\n<\/ul>\n<p><strong><u>SOUTH VENTILATION SHAFT OF THE STATION <\/u><\/strong>(Koumoundourou Street)<\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<\/li>\n<li>Masonry walls \u2013 plastering works.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Surface reinstatement works.<\/li>\n<li>Construction of perimeter wall at the expropriation boundaries.<\/li>\n<li>Installation of metal structures at levels +8.36 and +21.00.<\/li>\n<\/ul>\n<p><strong><u>NORTH VENTILATION SHAFT OF THE STATION <\/u><\/strong>(Dimitrakopoulou Street)<\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<strong>\u00a0<\/strong><\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Pile cap beam demolition.<\/li>\n<li>Construction of perimeter wall at the expropriation boundaries.<\/li>\n<li>Installation of metal structures at levels +8.08 and +24.98.<\/li>\n<\/ul>\n<p><strong><u>MELA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of the final lining of the NATM tunnel (vault + reverse arch).<\/li>\n<li>Concreting of the foundation slab.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of reinforcement and concreting of the perimeter walls of the permanent lining.<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS<\/u><\/strong><strong><u> STATION\u00a0 <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the main station.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Excavation and temporary retaining of entrance 1.<\/li>\n<li>Excavation and temporary retaining of entrance 2.<\/li>\n<li>Construction of architectural finishes (masonry walls, plastering, painting works, industrial flooring, floor filling, floor screed concrete works and installation of tiles at level -3, filling works at level -2, steel doors).<\/li>\n<li>High pressure water blasting at the diaphragm walls between the station and entrance 1 at the concourse level (-1).<\/li>\n<\/ul>\n<p><strong><u>ROLOI SHAFT &amp; <\/u><\/strong><strong><u>NATM ACCESS TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Slab cconcreting at level -7.50 (shed at the entry point of the connecting tunnel).<\/li>\n<li>Sealing of the temporary pumping station.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO STATION <\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Pile cap beam demolition.<\/li>\n<li>Backfilling \u2013 compaction works at street level.<\/li>\n<li>Installation of doors at the E\/M floor, at the concourse level and at the platform level.<\/li>\n<li>Installation of floor granite slabs at the platform level and at the concourse level.<\/li>\n<li>Painting works at staircases 7 and 8.<\/li>\n<li>Conservation of the Project\u2019s archaeological finds.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND SECTION OF THE STATION <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of floor granites.<\/li>\n<\/ul>\n<p><strong><u>STAIRCASE GALLERIES<\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining and secondary concrete.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of floor granite slabs at the southern staircase (landing at the concourse level).<\/li>\n<\/ul>\n<p><strong><u>KORAI SQUARE<\/u><\/strong><strong><u> ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, secondary concrete.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Construction of support system for wall-mounted granites in the access gallery.<\/li>\n<\/ul>\n<p><strong><u>BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY<\/u><\/strong><strong>\u00a0<\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining.<\/li>\n<\/ul>\n<p><strong>The following works are put on hold: <\/strong><\/p>\n<ul>\n<li>Backfilling \u2013 compaction related works.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Construction of support system for wall-mounted granites in the access gallery<\/li>\n<li>Secondary concrete in the area where the pebbled floor is exhibited.<\/li>\n<li>Floor screed concrete works at the connecting tunnel.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS) &amp; VENTILATION TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining.<\/li>\n<li>Sealing of the temporary pumping station.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Backfilling \u2013 compaction related works.<\/li>\n<li>Construction of new sidewalks at street level.<\/li>\n<li>Painting works at the shaft.<\/li>\n<li>Construction of industrial floor for machinery pedestals.<\/li>\n<\/ul>\n<p><strong><u>DELIGIANNI SHAFT<\/u><\/strong><\/p>\n<p><strong>\u00a0The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Excavation and temporary retaining up to the final level<\/li>\n<li>Waterproofing, construction of foundation slab and perimeter walls down to -3.0.<\/li>\n<\/ul>\n<p><strong><u>PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the foundation of the shaft\u2019s permanent lining<\/li>\n<li>Concreting of the permanent lining of the connecting tunnel.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<p>Concreting of the permanent lining of the shaft\u2019s perimeter walls (completed up to level +4.5).<\/p>\n","protected":false},"excerpt":{"rendered":"<p>TZAVELA SHAFT The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. MANIATIKA STATION STATION\u2019s OPEN CUT The following works have been completed: Completion of the permanent lining of the shaft. The following works are in progress: Waterproofing of the roof slab. Construction of shafts 4 and 7 at street level. Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1. Architectural finishes \u2013 Painting works at levels -4, -3, -2, -1. Industrial flooring at levels -4, -3, -2, -1. Installation of ceramic tiles at levels -4, -3, -2, -1. Installation of metal structures in room 3.12. Installation of doors. MAIN TUNNEL OF THE STATION (\u039d\u0391\u03a4\u039c) The following works have been completed: Completion of the permanent lining of the station\u2019s main tunnel. Secondary concreting in platforms. Installation of granites in platforms. The following works are in progress: Installation of items supporting the platforms\u2019 metal lining. UNDERGROUND NATM SECTIONS OF THE STATION (NATM) The following works have been completed: Completion of the construction of the permanent lining of the station\u2019s eastern lift. The following works are in progress: Installation of items supporting the platforms\u2019 metal lining. SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street) The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Masonry walls \u2013 plastering works. The following works are in progress: Surface reinstatement works. Construction of perimeter wall at the expropriation boundaries. Installation of metal structures at levels +8.36 and +21.00. NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street) The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel.\u00a0 The following works are in progress: Pile cap beam demolition. Construction of perimeter wall at the expropriation boundaries. Installation of metal structures at levels +8.08 and +24.98. MELA SHAFT The following works have been completed: Concreting of the final lining of the NATM tunnel (vault + reverse arch). Concreting of the foundation slab. The following works are in progress: Installation of reinforcement and concreting of the perimeter walls of the permanent lining. PIRAEUS STATION\u00a0 The following works have been completed: Concreting of the main station. The following works are in progress: Excavation and temporary retaining of entrance 1. Excavation and temporary retaining of entrance 2. Construction of architectural finishes (masonry walls, plastering, painting works, industrial flooring, floor filling, floor screed concrete works and installation of tiles at level -3, filling works at level -2, steel doors). High pressure water blasting at the diaphragm walls between the station and entrance 1 at the concourse level (-1). ROLOI SHAFT &amp; NATM ACCESS TUNNEL The following works have been completed: Sealing of the temporary pumping station. The following works are in progress: Slab cconcreting at level -7.50 (shed at the entry point of the connecting tunnel). Sealing of the temporary pumping station. DIMOTIKO THEATRO STATION MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE The following works have been completed: Sealing of the temporary pumping station. The following works are in progress: Pile cap beam demolition. Backfilling \u2013 compaction works at street level. Installation of doors at the E\/M floor, at the concourse level and at the platform level. Installation of floor granite slabs at the platform level and at the concourse level. Painting works at staircases 7 and 8. Conservation of the Project\u2019s archaeological finds. UNDERGROUND SECTION OF THE STATION The following works have been completed: Concreting of the permanent lining. The following works are in progress: Installation of floor granites. STAIRCASE GALLERIES The following works have been completed: Concreting of the permanent lining and secondary concrete. The following works are in progress: Installation of floor granite slabs at the southern staircase (landing at the concourse level). KORAI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Concreting of the permanent lining, secondary concrete. The following works are in progress: Construction of support system for wall-mounted granites in the access gallery. BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY\u00a0 The following works have been completed: Concreting of the permanent lining. The following works are put on hold: Backfilling \u2013 compaction related works. The following works are in progress: Construction of support system for wall-mounted granites in the access gallery Secondary concrete in the area where the pebbled floor is exhibited. Floor screed concrete works at the connecting tunnel. DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS) &amp; VENTILATION TUNNEL The following works have been completed: Concreting of the permanent lining. Sealing of the temporary pumping station. The following works are in progress: Backfilling \u2013 compaction related works. Construction of new sidewalks at street level. Painting works at the shaft. Construction of industrial floor for machinery pedestals. DELIGIANNI SHAFT \u00a0The following works have been completed: Excavation and temporary retaining up to the final level Waterproofing, construction of foundation slab and perimeter walls down to -3.0. PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL The following works have been completed: Concreting of the foundation of the shaft\u2019s permanent lining Concreting of the permanent lining of the connecting tunnel. The following works are in progress: Concreting of the permanent lining of the shaft\u2019s perimeter walls (completed up to level +4.5).<\/p>\n","protected":false},"author":8,"featured_media":17787,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-17789","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1.jpg",2560,1707,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1.jpg",2560,1707,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1.jpg",2560,1707,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1-300x200.jpg",300,200,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1-1024x683.jpg",960,640,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1-1536x1024.jpg",1536,1024,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1-2048x1366.jpg",2048,1366,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1-1140x760.jpg",1140,760,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/05\/AM_Peiraias_progress_Apr-2021-scaled-1-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"ivassalos","author_link":"https:\/\/www.emetro.gr\/?author=8"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"TZAVELA SHAFT The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. MANIATIKA STATION STATION\u2019s OPEN CUT The following works have been completed: Completion of the permanent lining of the shaft. The following works are in progress: Waterproofing of the roof slab. Construction of shafts 4&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17789","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/8"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=17789"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17789\/revisions"}],"predecessor-version":[{"id":30992,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17789\/revisions\/30992"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/17787"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=17789"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=17789"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=17789"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}