{"id":17723,"date":"2021-04-12T12:52:22","date_gmt":"2021-04-12T09:52:22","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=17723"},"modified":"2024-06-21T12:17:14","modified_gmt":"2024-06-21T09:17:14","slug":"march-2021","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=17723&lang=en","title":{"rendered":"MARCH 2021"},"content":{"rendered":"<p><strong><u>TZAVELA SHAFT<\/u><\/strong><strong>\u00a0<\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<\/li>\n<\/ul>\n<p><strong><u>MANIATIKA STATION <\/u><\/strong><\/p>\n<p><strong><u>STATION\u2019s OPEN CUT <\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Waterproofing of the roof slab.<\/li>\n<li>Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1.<\/li>\n<li>Architectural finishes \u2013 Painting works at levels -4, -3, -2, -1.<\/li>\n<li>Industrial flooring at levels -4, -3, -2, -1.<\/li>\n<\/ul>\n<p><strong><u>MAIN TUNNEL OF THE STATION<\/u><\/strong><strong><u> (<\/u><\/strong><strong><u>\u039d\u0391\u03a4\u039c<\/u><\/strong><strong><u>)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Permanent lining of the station\u2019s main tunnel.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Secondary concreting in platforms.<\/li>\n<\/ul>\n<p><strong><u>SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<\/li>\n<li>Masonry walls \u2013 plastering works.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Surface reinstatement works.<\/li>\n<li>Construction of perimeter wall at the expropriation boundaries.<\/li>\n<\/ul>\n<p><strong><u>NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Pile cap beam demolition.<\/li>\n<\/ul>\n<p><strong><u>MELA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Concreting of the final lining of the NATM tunnel (vault + reverse arch).<\/li>\n<li>Concreting of the foundation slab.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of reinforcement and concreting of the perimeter walls and the roof slab of the shaft\u2019s pumping station.<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS<\/u><\/strong><strong><u> STATION\u00a0 <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the main station<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Excavation and temporary retaining of entrance 1.<\/li>\n<li>Excavation and temporary retaining of entrance 2.<\/li>\n<li>Construction of architectural finishes (masonry walls, plastering, painting works, industrial flooring, floor filling, installation of tiles at level -3, filling works at level -2, steel doors).<\/li>\n<li>Installation of formwork, reinforcement and concreting of interior staircases.<\/li>\n<li>High pressure water blasting at the diaphragm walls between the station and entrance 1 at the concourse level (-1).<\/li>\n<\/ul>\n<p><strong><u>ROLOI SHAFT &amp; <\/u><\/strong><strong><u>NATM ACCESS TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Construction of permanent lining.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Removal of scaffoldings.<\/li>\n<li>Concrete repair works.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO STATION <\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<\/ul>\n<p><strong>The following works are put on hold: <\/strong><\/p>\n<ul>\n<li>Installation of doors at E\/M level.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Cleaning works.<\/li>\n<li>Backfilling \u2013 compaction works at street level.<\/li>\n<li>Installation of doors at the E\/M floor.<\/li>\n<li>Installation of floor and wall tiles in the personnel areas (ticketing level).<\/li>\n<li>Painting works at the concourse level.<\/li>\n<li>Installation of floor granite slabs at the platform level.<\/li>\n<li>Painting preparatory works at staircases 7 and 8.<\/li>\n<li>Conservation of the Project\u2019s archaeological finds.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND SECTION OF THE STATION <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, walls and platform slab.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of floor granites.<\/li>\n<\/ul>\n<p><strong><u>STAIRCASE GALLERIES<\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining and secondary concrete.<\/li>\n<\/ul>\n<p><strong><u>KORAI SQUARE<\/u><\/strong><strong><u> ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, secondary concrete.<\/li>\n<\/ul>\n<p><strong><u> BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY<\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining.<\/li>\n<\/ul>\n<p><strong>The following works are put on hold: <\/strong><\/p>\n<ul>\n<li>Backfilling \u2013 compaction related works<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Construction of support system for wall-mounted granites in the access gallery<\/li>\n<li>Preparation works for secondary concrete in the area where the pebbled floor is exhibited.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO VENTILATION SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Pile cap beam demolition at street level.<\/li>\n<li>Backfilling \u2013 compaction related works.<\/li>\n<li>Painting works at the shaft.<\/li>\n<\/ul>\n<p><strong><u>RALLIOS SHAFT VENTILLATION TUNNEL<\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining.<\/li>\n<\/ul>\n<p><strong><u>TRIPLE TRACK NATM TUNNEL<\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining.<\/li>\n<\/ul>\n<p><strong><u>DELIGIANNI SHAFT<\/u><\/strong><\/p>\n<p><strong>\u00a0The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Excavation and temporary retaining up to the final level<\/li>\n<li>Waterproofing, construction of foundation slab and perimeter walls down to -3.0.<\/li>\n<\/ul>\n<p><strong><u>PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the foundation of the shaft\u2019s permanent lining<\/li>\n<li>Concreting of the permanent lining of the connecting tunnel.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li style=\"list-style-type: none\">\n<ul>\n<li>Concreting of the shaft\u2019s perimeter walls (completed down<\/li>\n<li>to -4.5)<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n","protected":false},"excerpt":{"rendered":"<p>TZAVELA SHAFT\u00a0 The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. MANIATIKA STATION STATION\u2019s OPEN CUT The following works have been completed: Completion of the permanent lining of the shaft. The following works are in progress: Waterproofing of the roof slab. Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1. Architectural finishes \u2013 Painting works at levels -4, -3, -2, -1. Industrial flooring at levels -4, -3, -2, -1. MAIN TUNNEL OF THE STATION (\u039d\u0391\u03a4\u039c) The following works have been completed: Permanent lining of the station\u2019s main tunnel. The following works are in progress: Secondary concreting in platforms. SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street) The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Masonry walls \u2013 plastering works. The following works are in progress: Surface reinstatement works. Construction of perimeter wall at the expropriation boundaries. NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street) The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. The following works are in progress: Pile cap beam demolition. MELA SHAFT The following works have been completed: Concreting of the final lining of the NATM tunnel (vault + reverse arch). Concreting of the foundation slab. The following works are in progress: Installation of reinforcement and concreting of the perimeter walls and the roof slab of the shaft\u2019s pumping station. PIRAEUS STATION\u00a0 The following works have been completed: Concreting of the main station The following works are in progress: Excavation and temporary retaining of entrance 1. Excavation and temporary retaining of entrance 2. Construction of architectural finishes (masonry walls, plastering, painting works, industrial flooring, floor filling, installation of tiles at level -3, filling works at level -2, steel doors). Installation of formwork, reinforcement and concreting of interior staircases. High pressure water blasting at the diaphragm walls between the station and entrance 1 at the concourse level (-1). ROLOI SHAFT &amp; NATM ACCESS TUNNEL The following works have been completed: Construction of permanent lining. The following works are in progress: Removal of scaffoldings. Concrete repair works. DIMOTIKO THEATRO STATION MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE The following works have been completed: Sealing of the temporary pumping station. The following works are put on hold: Installation of doors at E\/M level. The following works are in progress: Cleaning works. Backfilling \u2013 compaction works at street level. Installation of doors at the E\/M floor. Installation of floor and wall tiles in the personnel areas (ticketing level). Painting works at the concourse level. Installation of floor granite slabs at the platform level. Painting preparatory works at staircases 7 and 8. Conservation of the Project\u2019s archaeological finds. UNDERGROUND SECTION OF THE STATION The following works have been completed: Concreting of the permanent lining, walls and platform slab. The following works are in progress: Installation of floor granites. STAIRCASE GALLERIES The following works have been completed: Concreting of the permanent lining and secondary concrete. KORAI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Concreting of the permanent lining, secondary concrete. BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Concreting of the permanent lining. The following works are put on hold: Backfilling \u2013 compaction related works The following works are in progress: Construction of support system for wall-mounted granites in the access gallery Preparation works for secondary concrete in the area where the pebbled floor is exhibited. DIMOTIKO THEATRO VENTILATION SHAFT The following works have been completed: Concreting of the permanent lining. The following works are in progress: Pile cap beam demolition at street level. Backfilling \u2013 compaction related works. Painting works at the shaft. RALLIOS SHAFT VENTILLATION TUNNEL The following works have been completed: Concreting of the permanent lining. TRIPLE TRACK NATM TUNNEL The following works have been completed: Concreting of the permanent lining. DELIGIANNI SHAFT \u00a0The following works have been completed: Excavation and temporary retaining up to the final level Waterproofing, construction of foundation slab and perimeter walls down to -3.0. PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL The following works have been completed: Concreting of the foundation of the shaft\u2019s permanent lining Concreting of the permanent lining of the connecting tunnel. The following works are in progress: Concreting of the shaft\u2019s perimeter walls (completed down to -4.5)<\/p>\n","protected":false},"author":8,"featured_media":17721,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-17723","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1.jpg",2560,1707,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1.jpg",2560,1707,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1.jpg",2560,1707,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1-300x200.jpg",300,200,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1-1024x683.jpg",960,640,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1-1536x1024.jpg",1536,1024,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1-2048x1366.jpg",2048,1366,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1-1140x760.jpg",1140,760,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-1-scaled-1-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"ivassalos","author_link":"https:\/\/www.emetro.gr\/?author=8"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"TZAVELA SHAFT\u00a0 The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. MANIATIKA STATION STATION\u2019s OPEN CUT The following works have been completed: Completion of the permanent lining of the shaft. The following works are in progress: Waterproofing of the roof slab. Masonry walls \u2013 plastering&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17723","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/8"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=17723"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17723\/revisions"}],"predecessor-version":[{"id":30993,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17723\/revisions\/30993"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/17721"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=17723"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=17723"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=17723"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}