{"id":17705,"date":"2021-04-01T10:49:32","date_gmt":"2021-04-01T07:49:32","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=17705"},"modified":"2024-06-21T12:17:45","modified_gmt":"2024-06-21T09:17:45","slug":"february-2021","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=17705&lang=en","title":{"rendered":"FEBRUARY 2021"},"content":{"rendered":"<p><strong><u>TZAVELA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft and of the connecting tunnel.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Masonry walls.<\/li>\n<\/ul>\n<p><strong><u>MANIATIKA STATION <\/u><\/strong><\/p>\n<p><strong><u>STATION\u2019s OPEN CUT <\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Waterproofing of the roof slab.<\/li>\n<li>Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1.<\/li>\n<li>Architectural finishes \u2013 Painting works at levels -4, -3<\/li>\n<li>Industrial flooring at levels -4, -3 and -2.<\/li>\n<\/ul>\n<p><strong><u>MAIN TUNNEL OF THE STATION<\/u><\/strong><strong><u> (<\/u><\/strong><strong><u>\u039d\u0391\u03a4\u039c<\/u><\/strong><strong><u>)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Permanent lining of the station\u2019s main tunnel.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Secondary concreting in platforms.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND NATM SECTIONS OF THE STATION (NATM)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of excavation works and temporary retaining of the east elevator.<\/li>\n<li>Completion of construction of the permanent lining of the east elevator of the station.<\/li>\n<\/ul>\n<p><strong><u>MELA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Waterproofing of the NATM connecting tunnel.<\/li>\n<li>Concreting of the final lining of the NATM tunnel (vault + reverse arch).<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Concreting of the foundation slab (pumping station) and of the perimeter walls.<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS<\/u><\/strong><strong><u> STATION\u00a0 <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Waterproofing of the main station.<\/li>\n<li>Concreting of the main station.<\/li>\n<li>Removal of all struts.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Construction of architectural finishes (masonry walls, plastering, painting works, floor filling, industrial flooring).<\/li>\n<li>Installation of formwork, reinforcement and concreting of interior staircases.<\/li>\n<li>Excavation and temporary retaining of access 1.<\/li>\n<li>Excavation of entrance 2.<\/li>\n<li>Installation of waterproofing at the roof slab.<\/li>\n<\/ul>\n<p><strong><u>ROLOI SHAFT &amp; <\/u><\/strong><strong><u>NATM ACCESS TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Construction of permanent lining.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Concreting of the shaft\u2019s roof slab (completed).<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO STATION <\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<\/ul>\n<p><strong>The following works are put on hold: <\/strong><\/p>\n<ul>\n<li>Installation of doors at E\/M level.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Cleaning works.<\/li>\n<li>Cement mortar laying works at the ticketing level and the E\/M floor.<\/li>\n<li>Installation of floor granite slabs at the platform level.<\/li>\n<li>Installation of floor and wall tiles in the personnel areas (ticketing level).<\/li>\n<li>Painting preparatory works at staircases 7 and 8.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND SECTION OF THE STATION <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, walls and platform slab.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of floor granites.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO VENTILATION SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining.<\/li>\n<\/ul>\n<p><strong><u>RALLIOS SHAFT VENTILLATION TUNNEL<\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<p>Repairs to concreting works and application of polyurethane.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>TZAVELA SHAFT The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. The following works are in progress: Masonry walls. MANIATIKA STATION STATION\u2019s OPEN CUT The following works have been completed: Completion of the permanent lining of the shaft. The following works are in progress: Waterproofing of the roof slab. Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1. Architectural finishes \u2013 Painting works at levels -4, -3 Industrial flooring at levels -4, -3 and -2. MAIN TUNNEL OF THE STATION (\u039d\u0391\u03a4\u039c) The following works have been completed: Permanent lining of the station\u2019s main tunnel. The following works are in progress: Secondary concreting in platforms. UNDERGROUND NATM SECTIONS OF THE STATION (NATM) The following works have been completed: Completion of excavation works and temporary retaining of the east elevator. Completion of construction of the permanent lining of the east elevator of the station. MELA SHAFT The following works have been completed: Waterproofing of the NATM connecting tunnel. Concreting of the final lining of the NATM tunnel (vault + reverse arch). The following works are in progress: Concreting of the foundation slab (pumping station) and of the perimeter walls. PIRAEUS STATION\u00a0 The following works have been completed: Waterproofing of the main station. Concreting of the main station. Removal of all struts. The following works are in progress: Construction of architectural finishes (masonry walls, plastering, painting works, floor filling, industrial flooring). Installation of formwork, reinforcement and concreting of interior staircases. Excavation and temporary retaining of access 1. Excavation of entrance 2. Installation of waterproofing at the roof slab. ROLOI SHAFT &amp; NATM ACCESS TUNNEL The following works have been completed: Construction of permanent lining. The following works are in progress: Concreting of the shaft\u2019s roof slab (completed). DIMOTIKO THEATRO STATION MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE The following works have been completed: Sealing of the temporary pumping station. The following works are put on hold: Installation of doors at E\/M level. The following works are in progress: Cleaning works. Cement mortar laying works at the ticketing level and the E\/M floor. Installation of floor granite slabs at the platform level. Installation of floor and wall tiles in the personnel areas (ticketing level). Painting preparatory works at staircases 7 and 8. UNDERGROUND SECTION OF THE STATION The following works have been completed: Concreting of the permanent lining, walls and platform slab. The following works are in progress: Installation of floor granites. DIMOTIKO THEATRO VENTILATION SHAFT The following works have been completed: Concreting of the permanent lining. RALLIOS SHAFT VENTILLATION TUNNEL The following works have been completed: Concreting of the permanent lining The following works are in progress: Repairs to concreting works and application of polyurethane.<\/p>\n","protected":false},"author":8,"featured_media":17695,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-17705","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1.jpg",2560,1411,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1.jpg",2560,1411,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1.jpg",2560,1411,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1-300x165.jpg",300,165,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1-1024x564.jpg",960,529,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1-1536x847.jpg",1536,847,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1-2048x1129.jpg",2048,1129,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1-1140x628.jpg",1140,628,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/04\/AM_Peiraias_progress_Feb-2021-scaled-1-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"ivassalos","author_link":"https:\/\/www.emetro.gr\/?author=8"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"TZAVELA SHAFT The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. The following works are in progress: Masonry walls. MANIATIKA STATION STATION\u2019s OPEN CUT The following works have been completed: Completion of the permanent lining of the shaft. The following works are in progress: Waterproofing&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17705","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/8"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=17705"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17705\/revisions"}],"predecessor-version":[{"id":30994,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17705\/revisions\/30994"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/17695"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=17705"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=17705"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=17705"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}