{"id":17636,"date":"2021-02-19T12:53:42","date_gmt":"2021-02-19T10:53:42","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=17636"},"modified":"2024-06-25T13:40:29","modified_gmt":"2024-06-25T10:40:29","slug":"january-2021-3","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=17636&lang=en","title":{"rendered":"JANUARY 2021"},"content":{"rendered":"<p>&nbsp;<\/p>\n<p><strong><u>MANIATIKA STATION <\/u><\/strong><\/p>\n<p><strong><u>STATION\u2019s OPEN CUT <\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Completion of the permanent lining of the shaft<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Waterproofing of the roof slab<\/li>\n<li>Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1<\/li>\n<li>Architectural finishes \u2013 Painting works at level -4<\/li>\n<li>Industrial flooring at levels -4, -3 and -2<\/li>\n<\/ul>\n<p><strong><u>MAIN TUNNEL OF THE STATION<\/u><\/strong><strong><u> (<\/u><\/strong><strong><u>\u039d\u0391\u03a4\u039c<\/u><\/strong><strong><u>)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Permanent lining of the station\u2019s main tunnel<\/li>\n<li>Permanent lining of the deepening area<\/li>\n<li>Permanent lining of the northern and southern headwall<\/li>\n<li>Construction of parapet walls and platform slabs<\/li>\n<li>Secondary grouting of the vault of the main station tunnel<\/li>\n<li>Filling of platform ducts with non-reinforced concrete.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Repair works of the station\u2019s concrete vault and painting works at level -5.<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS STATION\u00a0 <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Waterproofing works underneath the foundation and at the perimeter walls<\/li>\n<li>Concreting of platform and vertical parapet walls underneath the platforms.<\/li>\n<li>Concreting of perimeter walls, inner parapet walls, intermediate slabs and columns<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Removal of struts and walers of the 1<sup>st <\/sup>row<\/li>\n<li>Installation of formwork, reinforcement and concreting of the roof slab<\/li>\n<li>Commencement of architectural finishes \u2013 construction of masonry walls and performance of plastering works<\/li>\n<\/ul>\n<p><strong><u>ROLOI SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Construction of permanent lining (still pending is the termination at street level).<\/li>\n<\/ul>\n<p><strong><u>NATM ACCESS TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO STATION <\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<\/ul>\n<p><strong>The following works are put on hold: <\/strong><\/p>\n<ul>\n<li>Installation of doors at E\/M level.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Cleaning works<\/li>\n<li>Cement mortar laying works at the ticketing level<\/li>\n<li>Installation of floor granite slabs at the platform level<\/li>\n<li>Installation of floor tiles in the personnel areas (ticketing level)<\/li>\n<li>Preparatory works for painting at staircases 7 and 8<\/li>\n<li>Conservation of the archaeological finds of the Project.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND PART OF THE STATION <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, walls and platform slab.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Cement mortar laying works at the platform level.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><strong><u>STAIRCASE GALLERIES <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining and works related to secondary concreting.<\/li>\n<\/ul>\n<p><strong><u>KORAI SQUARE<\/u><\/strong><strong><u> ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>\u00a0<\/strong><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, secondary concrete.<\/li>\n<\/ul>\n<p><strong><u>BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Waterproofing of the permanent lining<\/li>\n<\/ul>\n<p><strong>The following works are put on hold: <\/strong><\/p>\n<ul>\n<li>Backfilling \u2013 compaction related works.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Secondary concrete at the access gallery.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><strong><u>DELIGIANNI SHAFT<\/u><\/strong><\/p>\n<p><strong>\u00a0<\/strong><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Excavation and temporary retaining up to the final level<\/li>\n<li>Waterproofing, construction of foundation slab and perimeter walls down to -3.0.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><strong><u>PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL <\/u><\/strong><\/p>\n<p><strong>\u00a0<\/strong><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Excavation &#8211; temporary retaining<\/li>\n<li>Concreting of the foundation of the shaft\u2019s permanent lining<\/li>\n<li>Concreting of the permanent lining of the connecting tunnel.<\/li>\n<\/ul>\n<p>&nbsp;<\/p>\n","protected":false},"excerpt":{"rendered":"<p>&nbsp; MANIATIKA STATION STATION\u2019s OPEN CUT The following works have been completed: Completion of the permanent lining of the shaft The following works are in progress: Waterproofing of the roof slab Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1 Architectural finishes \u2013 Painting works at level -4 Industrial flooring at levels -4, -3 and -2 MAIN TUNNEL OF THE STATION (\u039d\u0391\u03a4\u039c) The following works have been completed: Permanent lining of the station\u2019s main tunnel Permanent lining of the deepening area Permanent lining of the northern and southern headwall Construction of parapet walls and platform slabs Secondary grouting of the vault of the main station tunnel Filling of platform ducts with non-reinforced concrete. The following works are in progress: Repair works of the station\u2019s concrete vault and painting works at level -5. PIRAEUS STATION\u00a0 The following works have been completed: Waterproofing works underneath the foundation and at the perimeter walls Concreting of platform and vertical parapet walls underneath the platforms. Concreting of perimeter walls, inner parapet walls, intermediate slabs and columns The following works are in progress: Removal of struts and walers of the 1st row Installation of formwork, reinforcement and concreting of the roof slab Commencement of architectural finishes \u2013 construction of masonry walls and performance of plastering works ROLOI SHAFT The following works have been completed: Construction of permanent lining (still pending is the termination at street level). NATM ACCESS TUNNEL The following works have been completed: Concreting of the permanent lining. DIMOTIKO THEATRO STATION MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE The following works have been completed: Sealing of the temporary pumping station. The following works are put on hold: Installation of doors at E\/M level. The following works are in progress: Cleaning works Cement mortar laying works at the ticketing level Installation of floor granite slabs at the platform level Installation of floor tiles in the personnel areas (ticketing level) Preparatory works for painting at staircases 7 and 8 Conservation of the archaeological finds of the Project. UNDERGROUND PART OF THE STATION The following works have been completed: Concreting of the permanent lining, walls and platform slab. The following works are in progress: Cement mortar laying works at the platform level. \u00a0STAIRCASE GALLERIES The following works have been completed: Concreting of the permanent lining and works related to secondary concreting. KORAI SQUARE ENTRANCE AND ACCESS GALLERY \u00a0The following works have been completed: Concreting of the permanent lining, secondary concrete. BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Waterproofing of the permanent lining The following works are put on hold: Backfilling \u2013 compaction related works. The following works are in progress: Secondary concrete at the access gallery. \u00a0DELIGIANNI SHAFT \u00a0The following works have been completed: Excavation and temporary retaining up to the final level Waterproofing, construction of foundation slab and perimeter walls down to -3.0. \u00a0PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL \u00a0The following works have been completed: Excavation &#8211; temporary retaining Concreting of the foundation of the shaft\u2019s permanent lining Concreting of the permanent lining of the connecting tunnel. &nbsp;<\/p>\n","protected":false},"author":12,"featured_media":17628,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-17636","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1.jpg",2560,1686,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1.jpg",2560,1686,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1.jpg",2560,1686,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1-300x198.jpg",300,198,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1-1024x674.jpg",960,632,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1-1536x1012.jpg",1536,1012,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1-2048x1349.jpg",2048,1349,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1-1140x751.jpg",1140,751,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2021\/02\/IMG_5047-scaled-1-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"kkatri","author_link":"https:\/\/www.emetro.gr\/?author=12"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"&nbsp; MANIATIKA STATION STATION\u2019s OPEN CUT The following works have been completed: Completion of the permanent lining of the shaft The following works are in progress: Waterproofing of the roof slab Masonry walls \u2013 plastering works at levels -4, -3, -2 and -1 Architectural finishes \u2013 Painting works at level -4 Industrial flooring at levels&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17636","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/12"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=17636"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17636\/revisions"}],"predecessor-version":[{"id":19708,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17636\/revisions\/19708"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/17628"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=17636"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=17636"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=17636"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}