{"id":17497,"date":"2020-12-15T09:41:28","date_gmt":"2020-12-15T07:41:28","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=17497"},"modified":"2024-06-25T13:41:36","modified_gmt":"2024-06-25T10:41:36","slug":"november-2020","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=17497&lang=en","title":{"rendered":"NOVEMBER 2020"},"content":{"rendered":"<p>&nbsp;<\/p>\n<p><strong><u>TZAVELA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Permanent lining of the bottom of the shaft<\/li>\n<li>Permanent lining of the connecting tunnel<\/li>\n<li>Removal of temporary steel frames for the support of the TBM tunnel<\/li>\n<li>Permanent lining of the perimeter wall of the shaft<\/li>\n<li>Permanent lining of interior parapet wall and staircase<\/li>\n<li>Permanent lining of the slab at level +8.57<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><strong><u>MANIATIKA STATION <\/u><\/strong><\/p>\n<p><strong><u>STATION\u2019s C\/C <\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Waterproofing of perimeter parapet walls<\/li>\n<li>Permanent lining of the foundation (level -4)<\/li>\n<li>Permanent lining of E\/M slab (level -3)<\/li>\n<li>Permanent lining of the ticketing area slab (level -2)<\/li>\n<li>Permanent lining of staircace S4<\/li>\n<li>Permanent lining of E\/M slab (level -1)<\/li>\n<li>Permanent lining of perimeter parapet walls and columns<\/li>\n<li>Permanent lining of the roof slab and staircase S3<\/li>\n<li>Construction of perimeter parapet walls of the station\u2019s main entrance (at street level) and of the inclined part of the main entrance (shed).<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Waterproofing of the roof slab<\/li>\n<li>Construction of masonry walls and execution of plastering works at levels -4,<\/li>\n<\/ul>\n<p>-3, -2 and -1.<\/p>\n<ul>\n<li>Construction of secondary concrete parapet walls at level -1.<\/li>\n<li>Construction of waterproofing \u2013 permanent lining of the eastbound station lift<\/li>\n<\/ul>\n<p><strong><u>MAIN TUNNEL OF THE STATION<\/u><\/strong><strong><u> (<\/u><\/strong><strong><u>\u039d\u0391\u03a4\u039c<\/u><\/strong><strong><u>)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Permanent lining of the station\u2019s main tunnel<\/li>\n<li>Permanent lining of the deepening area<\/li>\n<li>Permanent lining of the northern and southern headwall<\/li>\n<li>Construction of parapet walls and platform slabs<\/li>\n<li>Secondary grouting of the vault of the main station tunnel<\/li>\n<li>Filling of platform ducts with non-reinforced concrete.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Repair works of the station\u2019s concrete vault and painting works at level -5.<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS STATION\u00a0 <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Waterproofing works under the foundation<\/li>\n<li>Concreting of the foundation slab and placing of non-reinforced concrete over the foundation.<\/li>\n<li>Concreting of platforms and vertical elements underneath the platforms.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of waterproofing at the station\u2019s perimeter parapet walls<\/li>\n<li>Concreting of the station\u2019s perimeter parapet walls<\/li>\n<li>Installation of formwork and reinforcement at the ticketing area slab<\/li>\n<li>Concreting of the ticketing area slab<\/li>\n<li>Removal of struts and sleepers of the 2<sup>nd<\/sup> and 5<sup>th<\/sup> rows<\/li>\n<li>Concreting of inner parapet walls and columns<\/li>\n<\/ul>\n<p><strong><u>ROLOI SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Construction of foundation and permanent lining of perimeter parapet walls (still pending is the termination at street level).<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Construction of the door frame and installation of roller shutter.<\/li>\n<\/ul>\n<p><strong><u>NATM ACCESS TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO STATION <\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Sealing of the temporary pumping station.<\/li>\n<\/ul>\n<p><strong>The following works are put on hold: <\/strong><\/p>\n<ul>\n<li>Installation of doors at E\/M level.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Cleaning works<\/li>\n<li>Painting works at the concourse and E\/M levels<\/li>\n<li>Cement mortar laying works at the platform level<\/li>\n<li>Conservation of the archaeological finds of the Project.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND PART OF THE STATION <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, parapet walls and platform slab.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Cement mortar laying works at the platform level.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><strong><u>STAIRCASE GALLERIES <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining and works related to secondary concreting.<\/li>\n<\/ul>\n<p><strong><u>KORAI SQUARE<\/u><\/strong><strong><u> ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, secondary concrete and waterproofing.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Backfilling \u2013 compaction related works.<\/li>\n<\/ul>\n<p><strong><u>BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level)<\/li>\n<li>Secondary concrete at the staircases.<\/li>\n<\/ul>\n<p><strong>The following works are put on hold: <\/strong><\/p>\n<ul>\n<li>Secondary concrete at the access gallery.<\/li>\n<li>Backfilling \u2013 compaction related works.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><strong><u>DELIGIANNI SHAFT<\/u><\/strong><\/p>\n<p><strong>\u00a0<\/strong><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Excavation and temporary retaining up to the final level<\/li>\n<li>Waterproofing, construction of foundation slab and perimeter parapet walls down to -3.0.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><strong><u>PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL <\/u><\/strong><\/p>\n<p><strong>\u00a0<\/strong><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Excavation &#8211; temporary retaining<\/li>\n<li>Concreting of the foundation of the shaft\u2019s permanent lining<\/li>\n<li>Concreting of the permanent lining of the connecting tunnel.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of reinforcement for the permanent lining and construction of formwork for the perimeter parapet walls, at the connection point between the connecting tunnel and the shaft.<\/li>\n<\/ul>\n","protected":false},"excerpt":{"rendered":"<p>&nbsp; TZAVELA SHAFT The following works have been completed: Permanent lining of the bottom of the shaft Permanent lining of the connecting tunnel Removal of temporary steel frames for the support of the TBM tunnel Permanent lining of the perimeter wall of the shaft Permanent lining of interior parapet wall and staircase Permanent lining of the slab at level +8.57 \u00a0MANIATIKA STATION STATION\u2019s C\/C The following works have been completed: Waterproofing of perimeter parapet walls Permanent lining of the foundation (level -4) Permanent lining of E\/M slab (level -3) Permanent lining of the ticketing area slab (level -2) Permanent lining of staircace S4 Permanent lining of E\/M slab (level -1) Permanent lining of perimeter parapet walls and columns Permanent lining of the roof slab and staircase S3 Construction of perimeter parapet walls of the station\u2019s main entrance (at street level) and of the inclined part of the main entrance (shed). The following works are in progress: Waterproofing of the roof slab Construction of masonry walls and execution of plastering works at levels -4, -3, -2 and -1. Construction of secondary concrete parapet walls at level -1. Construction of waterproofing \u2013 permanent lining of the eastbound station lift MAIN TUNNEL OF THE STATION (\u039d\u0391\u03a4\u039c) The following works have been completed: Permanent lining of the station\u2019s main tunnel Permanent lining of the deepening area Permanent lining of the northern and southern headwall Construction of parapet walls and platform slabs Secondary grouting of the vault of the main station tunnel Filling of platform ducts with non-reinforced concrete. The following works are in progress: Repair works of the station\u2019s concrete vault and painting works at level -5. PIRAEUS STATION\u00a0 The following works have been completed: Waterproofing works under the foundation Concreting of the foundation slab and placing of non-reinforced concrete over the foundation. Concreting of platforms and vertical elements underneath the platforms. The following works are in progress: Installation of waterproofing at the station\u2019s perimeter parapet walls Concreting of the station\u2019s perimeter parapet walls Installation of formwork and reinforcement at the ticketing area slab Concreting of the ticketing area slab Removal of struts and sleepers of the 2nd and 5th rows Concreting of inner parapet walls and columns ROLOI SHAFT The following works have been completed: Construction of foundation and permanent lining of perimeter parapet walls (still pending is the termination at street level). The following works are in progress: Construction of the door frame and installation of roller shutter. NATM ACCESS TUNNEL The following works have been completed: Concreting of the permanent lining. DIMOTIKO THEATRO STATION MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE The following works have been completed: Sealing of the temporary pumping station. The following works are put on hold: Installation of doors at E\/M level. The following works are in progress: Cleaning works Painting works at the concourse and E\/M levels Cement mortar laying works at the platform level Conservation of the archaeological finds of the Project. UNDERGROUND PART OF THE STATION The following works have been completed: Concreting of the permanent lining, parapet walls and platform slab. The following works are in progress: Cement mortar laying works at the platform level. \u00a0STAIRCASE GALLERIES The following works have been completed: Concreting of the permanent lining and works related to secondary concreting. KORAI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Concreting of the permanent lining, secondary concrete and waterproofing. The following works are in progress: Backfilling \u2013 compaction related works. BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level) Secondary concrete at the staircases. The following works are put on hold: Secondary concrete at the access gallery. Backfilling \u2013 compaction related works. \u00a0DELIGIANNI SHAFT \u00a0The following works have been completed: Excavation and temporary retaining up to the final level Waterproofing, construction of foundation slab and perimeter parapet walls down to -3.0. \u00a0PANEPISTIMIO SHAFT &amp; VENTILATION TUNNEL \u00a0The following works have been completed: Excavation &#8211; temporary retaining Concreting of the foundation of the shaft\u2019s permanent lining Concreting of the permanent lining of the connecting tunnel. The following works are in progress: Installation of reinforcement for the permanent lining and construction of formwork for the perimeter parapet walls, at the connection point between the connecting tunnel and the shaft.<\/p>\n","protected":false},"author":12,"featured_media":16739,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-17497","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1.jpg",1024,683,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1.jpg",1024,683,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1.jpg",1024,683,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1-300x200.jpg",300,200,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1.jpg",960,640,false],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1.jpg",1024,683,false],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1.jpg",1024,683,false],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1-1024x540.jpg",1024,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1.jpg",1024,683,false],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/AGHIA-VARVARA-24-1-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"kkatri","author_link":"https:\/\/www.emetro.gr\/?author=12"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"&nbsp; TZAVELA SHAFT The following works have been completed: Permanent lining of the bottom of the shaft Permanent lining of the connecting tunnel Removal of temporary steel frames for the support of the TBM tunnel Permanent lining of the perimeter wall of the shaft Permanent lining of interior parapet wall and staircase Permanent lining of&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17497","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/12"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=17497"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17497\/revisions"}],"predecessor-version":[{"id":19714,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/17497\/revisions\/19714"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/16739"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=17497"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=17497"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=17497"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}