{"id":16983,"date":"2020-09-18T12:03:01","date_gmt":"2020-09-18T09:03:01","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=16983"},"modified":"2024-06-25T11:37:18","modified_gmt":"2024-06-25T08:37:18","slug":"august-2020-2","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=16983&lang=en","title":{"rendered":"August 2020"},"content":{"rendered":"<p>&nbsp;<\/p>\n<p><strong>DIMOKRATIAS Station: <\/strong>The works for the reinstatement of the indoor and outdoor elevator have been executed.<\/p>\n<p><strong>AGHIA SOFIA<\/strong> <strong>Station<\/strong><strong>:<\/strong> The works for the construction of the permanent lining of the southern access as well as the works for the construction of masonry walls in the technical rooms and the network relocation works are in progress.<\/p>\n<p><strong>FLEMING<\/strong> <strong>Station<\/strong><strong>:<\/strong> Waterproofing works and painting works at the pumping station have been executed.<\/p>\n<p><strong>VOULGARI Station: <\/strong>The works for the installation of the indoor elevator and the works for the reinstatement of the firefighting network at level -2 have been executed.<\/p>\n<p><strong>DEPOT<\/strong><\/p>\n<p><strong>Building<\/strong> <strong>Complex<\/strong> <strong>\u0399<\/strong><strong>: <\/strong>Works for tiles installation at the train washing plant, building works at level +58.00 and works for the installation of the pressurized air supply network are in progress.<\/p>\n<p><strong>Building<\/strong> <strong>Complex<\/strong> <strong>\u0399\u0399<\/strong><strong>: <\/strong>The works for the fire fighting network at level +70.40 and the works for the installation of signaling equipment (line circuits) and signs are in progress.<\/p>\n<p><strong>TRACKWORK:<\/strong> The works for the construction of the floating slab of track 1 between EFKLIDIS and FLEMING Stations, the works for the installation of the double crossover at Analipsi Station, and track bed concreting works between VOULGARI and NEA ELVETIA Stations are in progress.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>&nbsp; DIMOKRATIAS Station: The works for the reinstatement of the indoor and outdoor elevator have been executed. AGHIA SOFIA Station: The works for the construction of the permanent lining of the southern access as well as the works for the construction of masonry walls in the technical rooms and the network relocation works are in progress. FLEMING Station: Waterproofing works and painting works at the pumping station have been executed. VOULGARI Station: The works for the installation of the indoor elevator and the works for the reinstatement of the firefighting network at level -2 have been executed. DEPOT Building Complex \u0399: Works for tiles installation at the train washing plant, building works at level +58.00 and works for the installation of the pressurized air supply network are in progress. Building Complex \u0399\u0399: The works for the fire fighting network at level +70.40 and the works for the installation of signaling equipment (line circuits) and signs are in progress. TRACKWORK: The works for the construction of the floating slab of track 1 between EFKLIDIS and FLEMING Stations, the works for the installation of the double crossover at Analipsi Station, and track bed concreting works between VOULGARI and NEA ELVETIA Stations are in progress.<\/p>\n","protected":false},"author":4,"featured_media":16857,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[79],"tags":[],"class_list":["post-16983","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-thessaloniki-base-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1.jpg",2560,1298,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1.jpg",2560,1298,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1.jpg",2560,1298,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1-300x152.jpg",300,152,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1-1024x519.jpg",960,487,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1-1536x779.jpg",1536,779,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1-2048x1038.jpg",2048,1038,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1-1140x578.jpg",1140,578,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/09\/THESSALONIKI_08_20-scaled-1-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"psymeonidou","author_link":"https:\/\/www.emetro.gr\/?author=4"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=79&#038;lang=en\" rel=\"category\">Thessaloniki Base Project progress<\/a>","rttpg_excerpt":"&nbsp; DIMOKRATIAS Station: The works for the reinstatement of the indoor and outdoor elevator have been executed. AGHIA SOFIA Station: The works for the construction of the permanent lining of the southern access as well as the works for the construction of masonry walls in the technical rooms and the network relocation works are in&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/16983","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/4"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=16983"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/16983\/revisions"}],"predecessor-version":[{"id":19911,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/16983\/revisions\/19911"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/16857"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=16983"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=16983"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=16983"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}