{"id":16525,"date":"2020-07-06T12:25:05","date_gmt":"2020-07-06T09:25:05","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=16525"},"modified":"2024-06-25T13:44:55","modified_gmt":"2024-06-25T10:44:55","slug":"june-2020","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=16525&lang=en","title":{"rendered":"JUNE 2020"},"content":{"rendered":"<p>&nbsp;<\/p>\n<p><strong><u>AGHIA VARVARA \u2013 KORYDALLOS \u2013 NIKEA STATIONS <\/u><\/strong><\/p>\n<ul>\n<li>The works for the construction of AGHIA VARVARA, KORYDALLOS and NIKEA Stations in Metro Line 3 Extension CON-12001 \u201cAGHIA MARINA\u2013PIRAEUS\u201d have been completed.<\/li>\n<li>Trial run for the upcoming delivery of the stations: 06\/07\/2020.<\/li>\n<\/ul>\n<p><strong><u>TZAVELA SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Permanent lining of the bottom of the shaft.<\/li>\n<li>Permanent lining of the connecting tunnel.<\/li>\n<li>Removal of the temporary metal frame for supporting TBM tunnel.<\/li>\n<li>Permanent lining of the perimeter shaft wall.<\/li>\n<\/ul>\n<p><strong>The<\/strong> <strong>following<\/strong> <strong>works<\/strong> <strong>are<\/strong> <strong>in<\/strong> <strong>progress<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Permanent lining of inner wall and staircase.<\/li>\n<\/ul>\n<p><strong><u>MANIATIKA STATION<\/u><\/strong><\/p>\n<p><strong><u>CUT AND COVER STATION <\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Waterproofing of the perimeter walls.<\/li>\n<li>Permanent lining of the foundation (level -4).<\/li>\n<li>Permanent lining of the E\/M slab (level -3).<\/li>\n<li>Permanent lining of the concourse slab (level -2).<\/li>\n<li>Permanent lining of staircase S<\/li>\n<li>Permanent lining of the E\/M slab (level -1).<\/li>\n<li>Permanent lining of perimeter walls and columns.<\/li>\n<li>Permanent lining of the roof slab and staircase S<\/li>\n<\/ul>\n<p><strong>The following works are in progress:<\/strong><\/p>\n<ul>\n<li>Waterproofing of the roof slab.<\/li>\n<li>Construction of perimeter walls at the main entrance of the station (street level) and of the inclined section of the main entrance (shed).<\/li>\n<li>Construction of masonry walls and plastering at levels -4, -3.<\/li>\n<\/ul>\n<p><strong><u>MAIN TUNNEL OF THE STATION<\/u><\/strong><strong><u> (<\/u><\/strong><strong><u>\u039d\u0391\u03a4\u039c<\/u><\/strong><strong><u>)<\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Permanent lining of the main tunnel of the station.<\/li>\n<li>Permanent lining of the deepening area.<\/li>\n<li>Permanent lining of the north and south headwall.<\/li>\n<li>Construction of platform walls and slabs.<\/li>\n<li>Secondary grouting of the vault of the main tunnel of the station.<\/li>\n<\/ul>\n<p><strong>In progress are the following works:<\/strong><\/p>\n<ul>\n<li>Filling of platform drainage channels using non-reinforced concrete.<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS<\/u><\/strong><strong><u> STATION<\/u><\/strong><\/p>\n<p><strong><u>STATION<\/u><\/strong><\/p>\n<p><strong>Completed are t<\/strong><strong>he following works<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Waterproofing works underneath the foundation.<\/li>\n<li>Concreting of the foundation slab by placing non-reinforced concrete over the foundation.<\/li>\n<\/ul>\n<p><strong>In progress are the following works:<\/strong><\/p>\n<ul>\n<li>Waterproofing of the station walls and of the north and south face areas.<\/li>\n<li>Concreting of the station perimeter walls and of the walls underneath the platforms.<\/li>\n<li>Concreting works under the platforms using non reinforced concrete.<\/li>\n<li>Concreting of platform slabs.<\/li>\n<li>Removal of struts, of 5<sup>th<\/sup> series sleepers and of 4<sup>th<\/sup> series furring brackets.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO STATION<\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE<\/u><\/strong><\/p>\n<p><strong>Pending<\/strong> <strong>are<\/strong> <strong>the<\/strong> <strong>following<\/strong> <strong>works<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Door installation at the E\/M level.<\/li>\n<\/ul>\n<p><strong>In<\/strong> <strong>progress<\/strong> <strong>are<\/strong> <strong>the<\/strong> <strong>following<\/strong> <strong>works<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Preservation of the archaeological finds of the Project.<\/li>\n<li>Brick structures at the mechanical floor level and at the concourse level.<\/li>\n<li>Preparation for painting works at platform level.<\/li>\n<li>Cleaning works.<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND STATION SECTION<\/u><\/strong><\/p>\n<p><strong>Completed<\/strong> <strong>are<\/strong> <strong>the<\/strong> <strong>following<\/strong> <strong>works<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Concreting of permanent lining, walls and of the platform<\/li>\n<\/ul>\n<p><strong><u>STAIRCASES TUNNELS<\/u><\/strong><\/p>\n<p><strong>The<\/strong> <strong>following<\/strong> <strong>works have been completed<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Concreting of permanent lining and secondary concrete.<\/li>\n<\/ul>\n<p><strong><u>KORAI SQUARE<\/u><\/strong><strong><u> ENTRANCE AND ACCESS TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works have been completed<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Concreting of permanent lining, secondary concreting and waterproofing works.<\/li>\n<\/ul>\n<p><strong><u>ENTRANCE AT P. BAKOYANNIS SQUARE AND ACCESS TUNNEL <\/u><\/strong><\/p>\n<p><strong>The following works have been completed:<\/strong><\/p>\n<ul>\n<li>Waterproofing and concreting of the permanent lining (the detail of the waterproofing at the exit &#8211; street level &#8211; is pending).<\/li>\n<li>Secondary concreting of the staircases.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><strong>Pending<\/strong> <strong>are<\/strong> <strong>the<\/strong> <strong>following<\/strong> <strong>works<\/strong><strong>:<\/strong><\/p>\n<ul>\n<li>Secondary concreting of the access tunnel.<\/li>\n<\/ul>\n<p>&nbsp;<\/p>\n<p>&nbsp;<\/p>\n","protected":false},"excerpt":{"rendered":"<p>&nbsp; AGHIA VARVARA \u2013 KORYDALLOS \u2013 NIKEA STATIONS The works for the construction of AGHIA VARVARA, KORYDALLOS and NIKEA Stations in Metro Line 3 Extension CON-12001 \u201cAGHIA MARINA\u2013PIRAEUS\u201d have been completed. Trial run for the upcoming delivery of the stations: 06\/07\/2020. TZAVELA SHAFT The following works have been completed: Permanent lining of the bottom of the shaft. Permanent lining of the connecting tunnel. Removal of the temporary metal frame for supporting TBM tunnel. Permanent lining of the perimeter shaft wall. The following works are in progress: Permanent lining of inner wall and staircase. MANIATIKA STATION CUT AND COVER STATION The following works have been completed: Waterproofing of the perimeter walls. Permanent lining of the foundation (level -4). Permanent lining of the E\/M slab (level -3). Permanent lining of the concourse slab (level -2). Permanent lining of staircase S Permanent lining of the E\/M slab (level -1). Permanent lining of perimeter walls and columns. Permanent lining of the roof slab and staircase S The following works are in progress: Waterproofing of the roof slab. Construction of perimeter walls at the main entrance of the station (street level) and of the inclined section of the main entrance (shed). Construction of masonry walls and plastering at levels -4, -3. MAIN TUNNEL OF THE STATION (\u039d\u0391\u03a4\u039c) The following works have been completed: Permanent lining of the main tunnel of the station. Permanent lining of the deepening area. Permanent lining of the north and south headwall. Construction of platform walls and slabs. Secondary grouting of the vault of the main tunnel of the station. In progress are the following works: Filling of platform drainage channels using non-reinforced concrete. PIRAEUS STATION STATION Completed are the following works: Waterproofing works underneath the foundation. Concreting of the foundation slab by placing non-reinforced concrete over the foundation. In progress are the following works: Waterproofing of the station walls and of the north and south face areas. Concreting of the station perimeter walls and of the walls underneath the platforms. Concreting works under the platforms using non reinforced concrete. Concreting of platform slabs. Removal of struts, of 5th series sleepers and of 4th series furring brackets. DIMOTIKO THEATRO STATION MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE Pending are the following works: Door installation at the E\/M level. In progress are the following works: Preservation of the archaeological finds of the Project. Brick structures at the mechanical floor level and at the concourse level. Preparation for painting works at platform level. Cleaning works. UNDERGROUND STATION SECTION Completed are the following works: Concreting of permanent lining, walls and of the platform STAIRCASES TUNNELS The following works have been completed: Concreting of permanent lining and secondary concrete. KORAI SQUARE ENTRANCE AND ACCESS TUNNEL The following works have been completed: Concreting of permanent lining, secondary concreting and waterproofing works. ENTRANCE AT P. BAKOYANNIS SQUARE AND ACCESS TUNNEL The following works have been completed: Waterproofing and concreting of the permanent lining (the detail of the waterproofing at the exit &#8211; street level &#8211; is pending). Secondary concreting of the staircases. \u00a0Pending are the following works: Secondary concreting of the access tunnel. &nbsp; &nbsp;<\/p>\n","protected":false},"author":12,"featured_media":16522,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-16525","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1.jpg",2560,1180,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1.jpg",2560,1180,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1.jpg",2560,1180,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1-300x138.jpg",300,138,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1-1024x472.jpg",960,443,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1-1536x708.jpg",1536,708,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1-2048x944.jpg",2048,944,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1-1140x525.jpg",1140,525,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/07\/IMG_20200622_141448-scaled-1-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"kkatri","author_link":"https:\/\/www.emetro.gr\/?author=12"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"&nbsp; AGHIA VARVARA \u2013 KORYDALLOS \u2013 NIKEA STATIONS The works for the construction of AGHIA VARVARA, KORYDALLOS and NIKEA Stations in Metro Line 3 Extension CON-12001 \u201cAGHIA MARINA\u2013PIRAEUS\u201d have been completed. Trial run for the upcoming delivery of the stations: 06\/07\/2020. TZAVELA SHAFT The following works have been completed: Permanent lining of the bottom of&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/16525","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/12"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=16525"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/16525\/revisions"}],"predecessor-version":[{"id":19915,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/16525\/revisions\/19915"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/16522"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=16525"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=16525"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=16525"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}