{"id":16124,"date":"2020-04-23T15:02:24","date_gmt":"2020-04-23T12:02:24","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=16124"},"modified":"2024-06-25T13:47:50","modified_gmt":"2024-06-25T10:47:50","slug":"march-2020","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=16124&lang=en","title":{"rendered":"MARCH 2020"},"content":{"rendered":"<p>&nbsp;<\/p>\n<p><strong><u>AGHIA VARVARA STATION <\/u><\/strong><\/p>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Wall and columns cladding (metal, glass etc.)<\/li>\n<li>Square reinstatement (granites, passageways)<\/li>\n<li>Signage, signalling and lighting<\/li>\n<li>Other reinstatement works at street level<\/li>\n<li>Station signs and other signs.<\/li>\n<\/ul>\n<p><strong><u>MEGALOU ALEXANDROU SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works are still pending: <\/strong><\/p>\n<ul>\n<li>Planting (street level).<\/li>\n<\/ul>\n<p><strong><u>TAXIARCHON SHAFT <\/u><\/strong><\/p>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Painting works<\/li>\n<li>Configuration at street level.<\/li>\n<\/ul>\n<p><strong><u>KORYDALLOS STATION <\/u><\/strong><\/p>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Wall and Columns cladding<\/li>\n<li>Installation of false ceilings<\/li>\n<li>Installation of balustrades<\/li>\n<li>Installation of roller shutters<\/li>\n<li>Installation of irrigation system at street level<\/li>\n<li>Installation of signage<\/li>\n<li>Installation of stainless steel structures<\/li>\n<li>Repair of painted surfaces and worn granites<\/li>\n<li>Installation of Station entrances\u2019 sheds<\/li>\n<li>Installation of lift at street level<\/li>\n<li>Configuration at street level (Eleftherias Square)<\/li>\n<\/ul>\n<p><strong><u>PISSIDIAS SHAFT <\/u><\/strong><\/p>\n<p><strong>Works have been completed. <\/strong><\/p>\n<p><strong><u>NIKEA STATION <\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION <\/u><\/strong><\/p>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Re-painting of cylindrical supports at level -3 of the platforms<\/li>\n<li>Re-painting of technical rooms at various Station levels<\/li>\n<li>Lining of roller shutter (ETALBOND) at the shed of the central entrance<\/li>\n<li>Cladding of vertical items using metal panels<\/li>\n<li>False ceilings<\/li>\n<li>Installation of signage<\/li>\n<li>Construction of sheds at the natural light shafts.<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS STATION\u00a0 <\/u><\/strong><\/p>\n<p><strong><u>STATION <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Installation and prestressing of struts for temporary retaining up to level 5.<\/li>\n<li>Installation of waterproofing and concreting of the foundation (bay 4).<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of reinforcement and concreting at section 1<\/li>\n<li>Station excavation at sections 2, 3 and 5 a, b (last phase)<\/li>\n<li>Improvement and installation of waterproofing and reinforcement at sections 2, 3.<\/li>\n<li>Installation and pre-loading of 4 struts of the temporary retaining at level 6.<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO STATION <\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE <\/u><\/strong><\/p>\n<p><strong>The following works are still pending: <\/strong><\/p>\n<ul>\n<li>Door installation at the E\/M floor.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Masonry walls at ticketing level<\/li>\n<li>Waterproofing at street level<\/li>\n<li>Backfilling \u2013 compaction related works<\/li>\n<li>Construction of bases of machinery at the E\/M floor<\/li>\n<li>Cleaning works<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND PART OF THE STATION <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, parapet walls and platform slab.<\/li>\n<\/ul>\n<p><strong><u>STAIRCASE GALLERIES <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining and works related to secondary concreting.<\/li>\n<\/ul>\n<p><strong><u>KORAI SQUARE ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining and secondary concrete.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Waterproofing of the top of the open trench.<\/li>\n<\/ul>\n<p><strong><u>BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level)<\/li>\n<li>Secondary concrete at the staircases.<\/li>\n<\/ul>\n<p><strong>The following works are put on hold: <\/strong><\/p>\n<ul>\n<li>Secondary concrete at the access gallery.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><\/p>\n<p><strong>\u00a0<\/strong><\/p>\n","protected":false},"excerpt":{"rendered":"<p>&nbsp; AGHIA VARVARA STATION The following works are in progress: Wall and columns cladding (metal, glass etc.) Square reinstatement (granites, passageways) Signage, signalling and lighting Other reinstatement works at street level Station signs and other signs. MEGALOU ALEXANDROU SHAFT The following works are still pending: Planting (street level). TAXIARCHON SHAFT The following works are in progress: Painting works Configuration at street level. KORYDALLOS STATION The following works are in progress: Wall and Columns cladding Installation of false ceilings Installation of balustrades Installation of roller shutters Installation of irrigation system at street level Installation of signage Installation of stainless steel structures Repair of painted surfaces and worn granites Installation of Station entrances\u2019 sheds Installation of lift at street level Configuration at street level (Eleftherias Square) PISSIDIAS SHAFT Works have been completed. NIKEA STATION MAIN STATION The following works are in progress: Re-painting of cylindrical supports at level -3 of the platforms Re-painting of technical rooms at various Station levels Lining of roller shutter (ETALBOND) at the shed of the central entrance Cladding of vertical items using metal panels False ceilings Installation of signage Construction of sheds at the natural light shafts. PIRAEUS STATION\u00a0 STATION The following works have been completed: Installation and prestressing of struts for temporary retaining up to level 5. Installation of waterproofing and concreting of the foundation (bay 4). The following works are in progress: Installation of reinforcement and concreting at section 1 Station excavation at sections 2, 3 and 5 a, b (last phase) Improvement and installation of waterproofing and reinforcement at sections 2, 3. Installation and pre-loading of 4 struts of the temporary retaining at level 6. DIMOTIKO THEATRO STATION MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE The following works are still pending: Door installation at the E\/M floor. The following works are in progress: Masonry walls at ticketing level Waterproofing at street level Backfilling \u2013 compaction related works Construction of bases of machinery at the E\/M floor Cleaning works UNDERGROUND PART OF THE STATION The following works have been completed: Concreting of the permanent lining, parapet walls and platform slab. STAIRCASE GALLERIES The following works have been completed: Concreting of the permanent lining and works related to secondary concreting. KORAI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Concreting of the permanent lining and secondary concrete. The following works are in progress: Waterproofing of the top of the open trench. BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY The following works have been completed: Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level) Secondary concrete at the staircases. The following works are put on hold: Secondary concrete at the access gallery. \u00a0 \u00a0<\/p>\n","protected":false},"author":12,"featured_media":16121,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-16124","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1.jpg",2560,1679,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1.jpg",2560,1679,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1.jpg",2560,1679,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1-300x197.jpg",300,197,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1-1024x672.jpg",960,630,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1-1536x1007.jpg",1536,1007,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1-2048x1343.jpg",2048,1343,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1-1140x748.jpg",1140,748,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/05\/IMG_0140-scaled-1-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"kkatri","author_link":"https:\/\/www.emetro.gr\/?author=12"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"&nbsp; AGHIA VARVARA STATION The following works are in progress: Wall and columns cladding (metal, glass etc.) Square reinstatement (granites, passageways) Signage, signalling and lighting Other reinstatement works at street level Station signs and other signs. MEGALOU ALEXANDROU SHAFT The following works are still pending: Planting (street level). TAXIARCHON SHAFT The following works are in&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/16124","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/12"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=16124"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/16124\/revisions"}],"predecessor-version":[{"id":19922,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/16124\/revisions\/19922"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/16121"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=16124"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=16124"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=16124"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}