{"id":16047,"date":"2020-03-09T13:13:58","date_gmt":"2020-03-09T11:13:58","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=16047"},"modified":"2024-06-25T13:48:20","modified_gmt":"2024-06-25T10:48:20","slug":"february-2020","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=16047&lang=en","title":{"rendered":"FEBRUARY 2020"},"content":{"rendered":"<p>&nbsp;<\/p>\n<p><strong><u>AGHIA VARVARA STATION <\/u><\/strong><\/p>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Installation of lifts in the station<\/li>\n<li>Wall and columns cladding (metal, glass etc.)<\/li>\n<li>Installation of balustrades<\/li>\n<li>Installation of handrails<\/li>\n<li>Other architectural finishes<\/li>\n<li>Installation of a fountain<\/li>\n<li>Planting and irrigation system<\/li>\n<li>Installation of false ceilings at the ticketing level<\/li>\n<li>Square reinstatement (Granites, Passageways, Marbles).<\/li>\n<\/ul>\n<p><strong><u>MEGALOU ALEXANDROU SHAFT<\/u><\/strong><\/p>\n<p><strong>The following works are still pending: <\/strong><\/p>\n<ul>\n<li>Planting (street level).<\/li>\n<\/ul>\n<p><strong><u>TAXIARCHON SHAFT <\/u><\/strong><\/p>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Painting works<\/li>\n<li>Configuration at street level.<\/li>\n<\/ul>\n<p><strong><u>KORYDALLOS STATION <\/u><\/strong><\/p>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Wall and Columns cladding<\/li>\n<li>Installation of false ceilings<\/li>\n<li>Installation of balustrades<\/li>\n<li>Installation of roller shutters<\/li>\n<li>Installation of irrigation system at street level<\/li>\n<li>Installation of signage<\/li>\n<li>Installation of Station entrances\u2019 sheds<\/li>\n<li>Installation of lift at street level<\/li>\n<li>Configuration at street level (Eleftherias Square)<\/li>\n<\/ul>\n<p><strong><u>PISSIDIAS SHAFT <\/u><\/strong><\/p>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Final reinstatement at street level<\/li>\n<\/ul>\n<p><strong><u>NIKEA STATION <\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION <\/u><\/strong><\/p>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Final reinstatement of the surrounding area<\/li>\n<li>Painting of parapet walls of the superstructure<\/li>\n<li>False ceilings<\/li>\n<li>Floor paving using granite slabs<\/li>\n<li>Wall cladding using metal panels<\/li>\n<li>Station signage.<\/li>\n<\/ul>\n<p><strong><u>PIRAEUS STATION\u00a0 <\/u><\/strong><\/p>\n<p><strong><u>STATION <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Installation and prestressing of struts for temporary retaining at all levels<\/li>\n<li>Installation of waterproofing and concreting of the foundation (bay 4).<\/li>\n<\/ul>\n<p><strong><u>DIMOTIKO THEATRO STATION <\/u><\/strong><\/p>\n<p><strong><u>MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE <\/u><\/strong><\/p>\n<p><strong>The following works are still pending: <\/strong><\/p>\n<ul>\n<li>Door installation at the E\/M floor.<\/li>\n<\/ul>\n<p><strong>The following works are in progress: <\/strong><\/p>\n<ul>\n<li>Masonry walls at ticketing level<\/li>\n<li>Waterproofing at street level<\/li>\n<li>Backfilling \u2013 compaction related works<\/li>\n<li>Cleaning works<\/li>\n<\/ul>\n<p><strong><u>UNDERGROUND PART OF THE STATION <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining, parapet walls and platform slab.<\/li>\n<\/ul>\n<p><strong><u>STAIRCASE GALLERIES <\/u><\/strong><\/p>\n<p><strong>The following works have been completed: <\/strong><\/p>\n<ul>\n<li>Concreting of the permanent lining and works related to secondary concreting.<\/li>\n<\/ul>\n<p><strong>\u00a0<\/strong><\/p>\n<p><strong>\u00a0<\/strong><\/p>\n","protected":false},"excerpt":{"rendered":"<p>&nbsp; AGHIA VARVARA STATION The following works are in progress: Installation of lifts in the station Wall and columns cladding (metal, glass etc.) Installation of balustrades Installation of handrails Other architectural finishes Installation of a fountain Planting and irrigation system Installation of false ceilings at the ticketing level Square reinstatement (Granites, Passageways, Marbles). MEGALOU ALEXANDROU SHAFT The following works are still pending: Planting (street level). TAXIARCHON SHAFT The following works are in progress: Painting works Configuration at street level. KORYDALLOS STATION The following works are in progress: Wall and Columns cladding Installation of false ceilings Installation of balustrades Installation of roller shutters Installation of irrigation system at street level Installation of signage Installation of Station entrances\u2019 sheds Installation of lift at street level Configuration at street level (Eleftherias Square) PISSIDIAS SHAFT The following works are in progress: Final reinstatement at street level NIKEA STATION MAIN STATION The following works are in progress: Final reinstatement of the surrounding area Painting of parapet walls of the superstructure False ceilings Floor paving using granite slabs Wall cladding using metal panels Station signage. PIRAEUS STATION\u00a0 STATION The following works have been completed: Installation and prestressing of struts for temporary retaining at all levels Installation of waterproofing and concreting of the foundation (bay 4). DIMOTIKO THEATRO STATION MAIN STATION \u2013 AGHIOU KONSTANTINOU SQUARE The following works are still pending: Door installation at the E\/M floor. The following works are in progress: Masonry walls at ticketing level Waterproofing at street level Backfilling \u2013 compaction related works Cleaning works UNDERGROUND PART OF THE STATION The following works have been completed: Concreting of the permanent lining, parapet walls and platform slab. STAIRCASE GALLERIES The following works have been completed: Concreting of the permanent lining and works related to secondary concreting. \u00a0 \u00a0<\/p>\n","protected":false},"author":12,"featured_media":16045,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[78],"tags":[],"class_list":["post-16047","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-peiraias-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1.jpg",2560,1707,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1.jpg",2560,1707,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1.jpg",2560,1707,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1-300x200.jpg",300,200,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1-1024x683.jpg",960,640,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1-1536x1024.jpg",1536,1024,true],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1-2048x1366.jpg",2048,1366,true],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1-1140x760.jpg",1140,760,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2020\/03\/IMG_7866-scaled-1-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"kkatri","author_link":"https:\/\/www.emetro.gr\/?author=12"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=78&#038;lang=en\" rel=\"category\">Piraeus Project progress<\/a>","rttpg_excerpt":"&nbsp; AGHIA VARVARA STATION The following works are in progress: Installation of lifts in the station Wall and columns cladding (metal, glass etc.) Installation of balustrades Installation of handrails Other architectural finishes Installation of a fountain Planting and irrigation system Installation of false ceilings at the ticketing level Square reinstatement (Granites, Passageways, Marbles). MEGALOU ALEXANDROU&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/16047","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/12"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=16047"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/16047\/revisions"}],"predecessor-version":[{"id":19923,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/16047\/revisions\/19923"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/16045"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=16047"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=16047"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=16047"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}