{"id":14826,"date":"2019-03-15T11:45:17","date_gmt":"2019-03-15T09:45:17","guid":{"rendered":"https:\/\/www.emetro.gr\/?p=14826"},"modified":"2024-06-25T14:26:17","modified_gmt":"2024-06-25T11:26:17","slug":"february-2019-2","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=14826&lang=en","title":{"rendered":"FEBRUARY 2019"},"content":{"rendered":"<p style=\"text-align: right;\">\n<p><strong>As regards the TRAMWAY NETWORK <\/strong><\/p>\n<ul>\n<li>The works for the construction of the Tramway corridor have been completed (trackwork \u2013 rails \u2013 catenary) <strong>have been completed<\/strong>.<\/li>\n<li>The trial run of the Tramway system commenced, while checking \u2013 arrangements \u2013 tests of the Tramway and catenary related installations <strong>are at the completion stage<\/strong>.<\/li>\n<li>Road signage &amp; signaling works at junctions, along the Tramway route, <strong>are in progress<\/strong>.<\/li>\n<li>E\/M works at the new Substation 16 (Civil Works have been completed), as well as the upgrading of Substation 1 <strong>are still pending<\/strong>.<\/li>\n<\/ul>\n<ol>\n<li><strong> As regards OTHER WORKS (reference to extended work fronts)<\/strong><\/li>\n<\/ol>\n<p>&#8211; <strong>At the Tramway stops:<\/strong><\/p>\n<ul>\n<li>Pending works related to the installation of urban equipment are under completion, while the installation of E\/M equipment is in progress.<\/li>\n<\/ul>\n<p>&#8211; <strong>Along the Tramway route to Piraeus<\/strong>, the following works are in progress:<\/p>\n<ul>\n<li><strong>At Lambraki bridge:<\/strong> Concrete maintenance works <u>commenced<\/u> and are in progress.<\/li>\n<li><strong>Karaiskaki stop:<\/strong> The installation of a canopy and the installation of the lift connecting the street level with the underground passage are in progress.<\/li>\n<li><strong>At SEF (Piece and Friendship Stadium), at Alikakou square, at Lambraki bridge and at the U-turn from Mikras Asias street towards Lambraki street:<\/strong> The installation of safety balustrades offering safe circulation of pedestrians and vehicles <u>is about to be completed<\/u>.<\/li>\n<\/ul>\n<p>&nbsp;<\/p>\n","protected":false},"excerpt":{"rendered":"<p>As regards the TRAMWAY NETWORK The works for the construction of the Tramway corridor have been completed (trackwork \u2013 rails \u2013 catenary) have been completed. The trial run of the Tramway system commenced, while checking \u2013 arrangements \u2013 tests of the Tramway and catenary related installations are at the completion stage. Road signage &amp; signaling works at junctions, along the Tramway route, are in progress. E\/M works at the new Substation 16 (Civil Works have been completed), as well as the upgrading of Substation 1 are still pending. As regards OTHER WORKS (reference to extended work fronts) &#8211; At the Tramway stops: Pending works related to the installation of urban equipment are under completion, while the installation of E\/M equipment is in progress. &#8211; Along the Tramway route to Piraeus, the following works are in progress: At Lambraki bridge: Concrete maintenance works commenced and are in progress. Karaiskaki stop: The installation of a canopy and the installation of the lift connecting the street level with the underground passage are in progress. At SEF (Piece and Friendship Stadium), at Alikakou square, at Lambraki bridge and at the U-turn from Mikras Asias street towards Lambraki street: The installation of safety balustrades offering safe circulation of pedestrians and vehicles is about to be completed. &nbsp;<\/p>\n","protected":false},"author":6,"featured_media":14781,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[572],"tags":[],"class_list":["post-14826","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-tram-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1.jpg",1306,849,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1.jpg",1306,849,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1.jpg",1306,849,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1-300x195.jpg",300,195,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1-1024x666.jpg",960,624,true],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1.jpg",1306,849,false],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1.jpg",1306,849,false],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1-1080x540.jpg",1080,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1-1140x741.jpg",1140,741,true],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2019\/03\/Untitled-1-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"vbardamaskou","author_link":"https:\/\/www.emetro.gr\/?author=6"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=572&#038;lang=en\" rel=\"category\">TRAM Project progress<\/a>","rttpg_excerpt":"As regards the TRAMWAY NETWORK The works for the construction of the Tramway corridor have been completed (trackwork \u2013 rails \u2013 catenary) have been completed. The trial run of the Tramway system commenced, while checking \u2013 arrangements \u2013 tests of the Tramway and catenary related installations are at the completion stage. Road signage &amp; signaling&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/14826","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/6"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=14826"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/14826\/revisions"}],"predecessor-version":[{"id":19736,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/14826\/revisions\/19736"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/14781"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=14826"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=14826"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=14826"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}