{"id":10233,"date":"2018-03-19T10:54:54","date_gmt":"2018-03-19T08:54:54","guid":{"rendered":"https:\/\/www.emetro.gr?p=10233"},"modified":"2024-06-25T13:03:32","modified_gmt":"2024-06-25T10:03:32","slug":"february-2018-4","status":"publish","type":"post","link":"https:\/\/www.emetro.gr\/?p=10233&lang=en","title":{"rendered":"February 2018"},"content":{"rendered":"<p style=\"text-align: right;\">\n<p>\u2022 Kritis shaft: The works related to the excavation and temporary retaining of struts down to level -4 have been completed. The excavation and temporary retaining of struts down to level -5 are in progress.<\/p>\n<p>\u2022 NOMARCHIA Station: The removal of reinforced concrete struts (roof level), as well as the excavation and retaining up to the 1st row of struts at the north access (at a part of Vas. Olgas Avenue) have been completed. The excavation of the north access (at a part of Vas. Olgas Avenue) and the backfilling of the widenings are in progress.<\/p>\n<p>\u2022 NOMARCHIA Crossover: The construction of floors is in progress.<\/p>\n<p>\u2022 ARETSOU Station: The construction of the station is in progress.<\/p>\n<p>\u2022 NEA KRINI Station: Masonry works are in progress.<\/p>\n<p>\u2022 MIKRA Station (&amp; crossovers) \u2013 2nd crossover: Works related to the waterproofing of the roof slab and masonry works have been completed. Plastering works are in progress.<\/p>\n<p>\u2022 MIKRA Forestation: The construction of the permanent lining has been completed. Waterproofing works are in progress (sections 1 and 2).<\/p>\n<p>\u2022 Terminal Shaft: The construction of the permanent lining has been completed, while the construction of the staircase inside the shaft is in progress.<\/p>\n<p>\u2022 TBM tunnels: Completion of tunnel 2 boring works along \u201cKalamaria- Nomarchia\u201d tunnel section by TBM2 (\u2018Elli\u2019). In progress is tunnel 1 boring works along \u201cKalamaria-Nomarchias Crossover\u201d tunnel section by TBM1 (\u201cFrixos\u201d).<\/p>\n","protected":false},"excerpt":{"rendered":"<p>\u2022 Kritis shaft: The works related to the excavation and temporary retaining of struts down to level -4 have been completed. The excavation and temporary retaining of struts down to level -5 are in progress. \u2022 NOMARCHIA Station: The removal of reinforced concrete struts (roof level), as well as the excavation and retaining up to the 1st row of struts at the north access (at a part of Vas. Olgas Avenue) have been completed. The excavation of the north access (at a part of Vas. Olgas Avenue) and the backfilling of the widenings are in progress. \u2022 NOMARCHIA Crossover: The construction of floors is in progress. \u2022 ARETSOU Station: The construction of the station is in progress. \u2022 NEA KRINI Station: Masonry works are in progress. \u2022 MIKRA Station (&amp; crossovers) \u2013 2nd crossover: Works related to the waterproofing of the roof slab and masonry works have been completed. Plastering works are in progress. \u2022 MIKRA Forestation: The construction of the permanent lining has been completed. Waterproofing works are in progress (sections 1 and 2). \u2022 Terminal Shaft: The construction of the permanent lining has been completed, while the construction of the staircase inside the shaft is in progress. \u2022 TBM tunnels: Completion of tunnel 2 boring works along \u201cKalamaria- Nomarchia\u201d tunnel section by TBM2 (\u2018Elli\u2019). In progress is tunnel 1 boring works along \u201cKalamaria-Nomarchias Crossover\u201d tunnel section by TBM1 (\u201cFrixos\u201d).<\/p>\n","protected":false},"author":4,"featured_media":10197,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[544],"tags":[],"class_list":["post-10233","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-kalamaria-project-progress-en"],"rttpg_featured_image_url":{"full":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18.jpg",1024,768,false],"landscape":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18.jpg",1024,768,false],"portraits":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18.jpg",1024,768,false],"thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18-150x150.jpg",150,150,true],"medium":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18-300x225.jpg",300,225,true],"large":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18.jpg",960,720,false],"1536x1536":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18.jpg",1024,768,false],"2048x2048":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18.jpg",1024,768,false],"ashe-slider-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18-1024x540.jpg",1024,540,true],"ashe-full-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18.jpg",1024,768,false],"ashe-list-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18-300x300.jpg",300,300,true],"ashe-grid-thumbnail":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18-500x330.jpg",500,330,true],"ashe-single-navigation":["https:\/\/www.emetro.gr\/wp-content\/uploads\/2018\/03\/KALAMARIA_2_18-75x75.jpg",75,75,true]},"rttpg_author":{"display_name":"psymeonidou","author_link":"https:\/\/www.emetro.gr\/?author=4"},"rttpg_comment":0,"rttpg_category":"<a href=\"https:\/\/www.emetro.gr\/?cat=544&#038;lang=en\" rel=\"category\">Kalamaria Project progress<\/a>","rttpg_excerpt":"\u2022 Kritis shaft: The works related to the excavation and temporary retaining of struts down to level -4 have been completed. The excavation and temporary retaining of struts down to level -5 are in progress. \u2022 NOMARCHIA Station: The removal of reinforced concrete struts (roof level), as well as the excavation and retaining up to&hellip;","_links":{"self":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/10233","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/users\/4"}],"replies":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=10233"}],"version-history":[{"count":1,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/10233\/revisions"}],"predecessor-version":[{"id":20053,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/posts\/10233\/revisions\/20053"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=\/wp\/v2\/media\/10197"}],"wp:attachment":[{"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=10233"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=10233"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.emetro.gr\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=10233"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}