Piraeus Project progress

June 2016

AGHIA VARVARA Station: The works for the removal of the precast segments of the false tunnel and the last ring have been completed. Works for the industrial floors and fillings are in progress. At M. Alexandrou Shaft, in progress are the excavation and temporary retaining works. NIKEA Station: The works…
Μάθε Περισσότερα

May2016

At the beginning of the extension, at the NATM double track tunnel, phase A’ of the tunnel excavation from TBM shaft to Aghia Marina is in progress. At Komninou shaft, the PUO network diversions and the archaeological trenches have been completed, while the works related to the worksite occupation and…
Μάθε Περισσότερα

March 2016

AGHIA VARVARA Station: The construction of the ticketing level slab was completed. At Taxiarchon shaft, the excavation of the 7th level was completed. NIKEA Station: The works for the permanent lining of the station were completed. More specifically: construction of the invert (reverse arch) construction of side walls construction of…
Μάθε Περισσότερα

February 2016

AGHIA VARVARA Station: The works for the construction of walls and platform floors were completed. At Megalou Alexandrou shaft, the worksite occupation and the traffic arrangements were completed. Preparatory works concerning excavation are in progress. NIKEA Station: The works for the TBM maintenance and the permanent lining of the station…
Μάθε Περισσότερα

January 2016

AGHIA VARVARA Station: The works for the waterproofing, construction of walls and platform floors, of perimeter walls up to the ticket issuing level, as well as the works for the construction of walls up to the roof level are in progress. Taxiarhon Shaft: The excavation works along with the works…
Μάθε Περισσότερα

December 2015

AGHIA VARVARA Station: The works for the removal of the pseudo-tunnel and the last ring’s precast segments are in progress; NIKEA Station: The works for the installation of the station’s escalators from the concourse to the platform level are in progress; MANIATIKA Station: The excavation and temporary retaining works of…
Μάθε Περισσότερα

November 2015

KORYDALLOS Station: The works for the waterproofing of the station are in progress. MANIATIKA Station: The excavation and temporary retaining works of phase A1 (eastern gallery) and phase A2 of the southern front of the station’s main tunnel are in progress. PIRAEUS Station: The preparation works for the construction of…
Μάθε Περισσότερα

October 2015

AGHIA VARVARA Station: The works for the removal of precast segments of the false tunnel are in progress; MANIATIKA Station: In progress are the excavation and temporary retaining works of phase A1 (south front – eastern gallery and north front – western gallery) of the station’s main tunnel. In progress…
Μάθε Περισσότερα

September 2015

AGHIA VARVARA Station: The works for the construction of perimeter walls and columns up to the mechanical floor level, as well as the works for the construction of the mechanical floor slab are in progress; NIKEA Station: The construction of a part of the roof slab of the main Station,…
Μάθε Περισσότερα

August 2015

AGHIA VARVARA Station: The construction works and the works for stressing the prestressed anchors at Taxiarchon Shaft are about to be completed; KORUDALLOS Station: The works for waterproofing the station are in progress; NIKEA Station: The TBM maintenance works are in progress; PIRAEUS Station: The works for the construction of…
Μάθε Περισσότερα