Year: 2014

THESSALONIKI METRO – Response to ΤΕΕ/ΤΚΜ concerning the archaeological finds in VENIZELOU STATION

Through its recent Press Release (15.07.2014), the Section of Central Macedonia of the Technical Chamber of Greece (TEE/TKM) criticizes ATTIKO METRO S.A. (AM) in the most unfair and unacceptable way, even using censorious wording, on the occasion of the archaeological finds revealed in VENIZELOU Station. In response to the allegations…
Μάθε Περισσότερα

June 2014

NIKEA Station: The excavation and muck disposal, as well as the construction of the temporary retaining (shotcrete, prestressed anchors, metal struts) at levels 5 and 6 of the main Station were completed. The excavation and disposal of excavation spoils of the main Station (levels 7, 8 and final excavation level),…
Μάθε Περισσότερα

June 2014

DIMOCRATIAS Station: The construction of conventional parapet walls southwards is in progress; SINTRIVANI Station: The excavation works at level 2 were completed, while the construction of slab at level 3, the construction of NATM ventilation tunnel and the archaeological excavation works at the northern access are in progress; PANEPISTIMIO Station:…
Μάθε Περισσότερα

June 2014

The works for the relocation of Trolleybus line No. 20 have commenced (from Vas. Georgiou street to Bouboulinas street); The works for the relocation of PUO networks (i.e. of the sewage pipe at Grigoriou Lambraki street) and of PPC networks at SEF (Piece and Friendship Stadium) stop area and at…
Μάθε Περισσότερα

THESSALONIKI METRO – The works for the construction of the second Station on the extension to Kalamaria have commenced

The works for the construction of NEA KRINI Station on the Metro extension to Kalamaria have started today. This is the second worksite where the contractor is now executing construction works, the first one being the TBM start-up shaft. The grandest transport infrastructure project in the city of Thessaloniki is…
Μάθε Περισσότερα

May 2014

KORYDALLOS Station: The works for the general excavation of the Station and the works for the improvement of the foundation invert – placement of a drainage layer have been completed. Waterproofing works, the works for the placement of reinforcement and foundation slab concreting works are in progress. NIKEA Station: Excavation…
Μάθε Περισσότερα

May 2014

NEW RAILWAY Station: Civil works were completed. AGHIA SOFIA Station: The archaeological excavation at the southern part of the station is in progress. SINTRIVANI Station: Excavation works at level 3, as well as the works for the construction of a NATM ventilation tunnel, are in progress. PAPAFI Station: Excavation works…
Μάθε Περισσότερα

May 2014

Traffic arrangements were completed at the current phase in the Central district and district A’ of Piraeus Municipality; The urban planning works at the sidewalk of Grigoriou Lambraki street are in progress; The technical works at various locations of the Tramway route (at Peace and Friendship (SEF) terminal Tramway stop,…
Μάθε Περισσότερα