Year: 2018

June 2018

• Kritis shaft: The permanent lining of the pumping station is completed. • NOMARCHIA Station: The permanent lining at section 7 of the perimeter structures (ventilation shafts) and the backfilling and construction of the PUO networks in the area of the north access have been completed. Granite flooring, phase D1…
Μάθε Περισσότερα

June 2018

• NEW RAILWAY Station: E/M installations in progress (water network). • DIMOKRATIAS Station: The installation of metal doors at levels -1 and -2 of the station and the backfilling of the south access of the station are completed. The construction of the station’s walls and the implementation of traffic regulation…
Μάθε Περισσότερα

June 2018

A. With regard to the TRAMWAY CORRIDOR: • At Piraeus: – The following activities are in progress, which complete the Tramway Line extension to Piraeus: the construction of the Tramway corridor at Vas. Georgiou street (from the end of Tinaneios (Tinan) garden to Akti Miaouli), as well as the installation…
Μάθε Περισσότερα

June 2018

• Komninou Shaft: The works for the construction of a staircase is in progress. • AGHIA VARVARA Station: In progress are the preliminary activities for the commencement of the architectural works in M. Alexandou Shaft. At recess 4+867, the works for the installation of the metal structure in the TBM…
Μάθε Περισσότερα

THESSALONIKI METRO: SINTRIVANI Station / EXPO Abolition of Worksite Occupation/Removal of Fences Reinstatement of Traffic

As of Saturday July 21st 2018, the occupied worksite area on the westbound traffic lane of Egnatia street will be released at SINTRIVANI Metro Station / EXPO, in front of Thessaloniki International Fair (EXPO) facilities. Thus, the traffic on Egnatia street will be normalized with two lanes. At the same…
Μάθε Περισσότερα