Year: 2015

July 2015

NOMARCHIA Station and Crossover: The works for the diversion of PUO networks are in progress. The works for the construction of piles are at an advanced stage; KALAMARIA Station: Works for the construction of temporary retaining piles are in progress; ARETSOU Station: Investigation trenches are in progress; NEA KRINI Station:…
Μάθε Περισσότερα

June 2015

AGHIA VARVARA Station: The works for the construction of columns down to the concourse level have been completed, while the works for the construction of access 3 are in progress; KORYDALLOS Station: The removal of the launch cradle and the TBM false tunnel precast segments has been completed. The undisturbed…
Μάθε Περισσότερα

June 2015

The works for the relocation of the sewage network located at the adjacent sidewalk of Omiridou Skylitsi street (from Ippodamias square – 34th Syntagmatos street), of the two sewage pressure pipes at Vas. Georgiou street and of the stormwater network in Mikras Asias street have been completed. The works for…
Μάθε Περισσότερα

June 2015

NOMARCHIA Station and Crossover: The works for the construction of temporary retaining piles are at an advanced stage; KALAMARIA Station: Works for the construction of temporary retaining piles are in progress; NEA KRINI Station: Works for the retaining of the station are in progress (installation of struts at the 2nd…
Μάθε Περισσότερα

May 2015

AGHIA VARVARA Station: The roof slab construction works are in progress; KORYDALLOS Station: Works for the construction of Station access piles have been completed, while the partial relocation of the TBM worksite installations is in progress; NIKEA Station: The works for the concreting of columns up to the mechanical floor…
Μάθε Περισσότερα

May 2015

The works for the relocation of the sewage network located at the adjacent sidewalk of M. Asias Street have been completed. Works for the relocation of sewage and natural gas networks in Vas. Georgiou Street have commenced and are in progress. The works for the relocation of EYDAP sewage &…
Μάθε Περισσότερα

May 2015

PANEPISTIMIO Station: Works for the construction of the foundation micro-piles have been completed. Works for the construction of the foundation slab have been completed; EFKLIDIS Station: Works for the installation of escalators are at an advanced stage; DEPOT: Works for the installation of the ground floor slab of complex I…
Μάθε Περισσότερα

May 2015

NOMARCHIA Station and Crossover: Construction works for the implementation of the traffic arrangements – Phase A have commenced, while works for the diversion of PUO networks are at an advanced stage. Piling works for the temporary retaining are in progress. The assembly of the building crane has been completed; KALAMARIA…
Μάθε Περισσότερα