Year: 2018

SEPTEMBER 2018

Kritis shaft: The works for the construction of the perimeter permanent lining continue, while the works for the construction of connecting tunnels are in progress. NOMARCHIA Station: The works for the construction of platforms are at an advanced stage, while the works for the construction of the lining of indoor walls are in progress. KALAMARIA […]
Read More

SEPTEMBER 2018

In PIRAEUS The works for the Multi-Channelled Layout and the Overhead Traction Line are at a completion stage. Civil works have been completed, while E/M works in the new Substation no. 16 are on hold. OTHER WORKS (extensive fronts of works) Along the Tramway route in Piraeus The works for the reinstatement of the urban […]
Read More

SEPTEMBER 2018

NEW RAILWAY Station: The works for the installation of E/M systems (fire extinguishing, water supply), as well as the construction of indoor partitions, are in progress. DIMOKRATIAS Station (station and crossover): The works for the installation of doors at the station and well as painting works are in progress. VENIZELOU Station: The works for burying […]
Read More

SEPTEMBER 2018

Two-track NATM tunnel: The works for the permanent lining of the tunnel’s vault have been completed. TBM Access Shaft: The works for the excavation and temporary retaining of the shaft have been completed together with the works for the construction of the foundation slab and the perimeter walls. Komninou Shaft: The works for the permanent […]
Read More

AUGUST 2018

Kritis shaft: The works for the construction of forepoles have been completed. NOMARCHIA Station: The works for the construction of the platform are in progress. KALAMARIA Station: Waterproofing works, as well as works for the permanent lining of the east access and pits, are in progress. ARETSOU Station: In progress are the following works: installation […]
Read More

AUGUST 2018

Base Project NEW RAILWAY Station: the configuration of the surrounding area is in progress. DIMOKRATIAS Station (station and crossover): The works for the reinstatement of the south sidewalk of Monastiriou Street, as well as the subsequent traffic arrangement, are in progress. VENIZELOU Station: The necessary works for the subsequent traffic arrangement have been completed, while […]
Read More

AUGUST 2018

[responsivevoice_button voice=”UK English Female” buttontext=”Listen to post”] A. With regard to the TRAMWAY CORRIDOR and the Overhead Traction Line: Works at the Tramway corridor (trackwork – rails and Catenary poles) have been completed throughout the Project, in particular: At Piraeus: From the beginning, at Neo Faliro stop and through Ethnarhou Makariou street – Papandreou bridge […]
Read More

AUGUST 2018

KORYDALLOS Station: In progress are the works for the waterproofing and permanent lining of the station’s accesses, as well as the works for the installation of doors, metal panels and the dismantling of piles and cap beams. Pissidias shaft: In progress are the works for the construction of the final lining of the bearing structure […]
Read More

“The Metro in our city” with its first vehicle

“The Metro in our city” with its first vehicle Three Metro worksites freely accessible during the opening ceremony of the 83rd International Fair of Thessaloniki Once again this year Attiko Metro S.A participates in the International Fair of Thessaloniki, with a rich program of information and educational activities, as well as with other concurrent events, […]
Read More

LINE 4 ATHENS METRO SECTION Α’ “ALSOS VEIKOU – GOUDI”

On Thursday September 6th, 2018, the tender documents and drawings for Stage B’ of the tender were delivered to the bidders who were pre-selected during stage A’ of the same tender, and namely to the following entities: ΤΕΡΝΑ ΑΕ- VINCI-SIEMENS AG “TVS” J+P AVAX ΑΕ- GHELLA SpA –ALSTOM TRANSPORT S.A. AKTOR ΑΤΕ – ANSALDO STP […]
Read More