Year: 2015

September 2015

The works for the relocation of sewage networks at Omiridou Skylitsi street, between Ippodamias & 34th Syntagmatos streets, have been completed. In progress are the relocations of the following networks: sewage and EPA at Vassileos Georgiou concurrently with the archaeological works, EYDAP water supply networks at the sidewalk adjacent to…
Μάθε Περισσότερα

September 2015

NOMARCHIA Station: Works for the excavation of station level -1 and works for the diversion of PUO networks are in progress; NOMARCHIA Crossover: Works for the construction of perimeter retaining piles and works for the diversion of PUO networks are in progress; KALAMARIA Station: Works related to the implementation of…
Μάθε Περισσότερα

August 2015

AGHIA VARVARA Station: The construction works and the works for stressing the prestressed anchors at Taxiarchon Shaft are about to be completed; KORUDALLOS Station: The works for waterproofing the station are in progress; NIKEA Station: The TBM maintenance works are in progress; PIRAEUS Station: The works for the construction of…
Μάθε Περισσότερα

August 2015

Completed are the relocations of OTE networks at the sidewalk of Grigoriou Lambraki street adjacent to the Tramway corridor and the dismantling of ILPAP networks from Ethnikisi Antistasseos Street. In progress are the relocations of sewage and EPA networks along with the archaeological works at Vassileos Georgiou street, as well…
Μάθε Περισσότερα

August 2015

NOMARCHIA Station: The works for the construction of retaining piles at the perimeter of the station were completed. The works for the construction of a pile cap beam are in progress; KALAMARIA Station: Works for the construction of piles at the western part of the station are in progress; NEA…
Μάθε Περισσότερα

July 2015

AGHIA VARVARA Station: The works for the construction of the roof slab are in progress; NIKEA Station: The TBM maintenance works and those for the construction of a portion of the main station’s roof slab are in progress; MANIATIKA Station: In progress are the works for the construction of the…
Μάθε Περισσότερα

July 2015

In progress are the relocations of the following networks: sewage and EPA at Vassileos Georgiou street, EYDAP sewage & water supply– EPA and OTE at the sidewalk of Grigoriou Lambraki street adjacent to the Tramway corridor, and finally the sewage network at Omiridou Skylitsi street; Archaeological finds were revealed at…
Μάθε Περισσότερα