- Piles constructed and excavations performed at the TBM start-up shaft at Micra;
- The Supplementary Geotechnical Survey was completed concerning all locations of the Project;
- The preparation of designs for the PUO networks relocation and diversion, the designs concerning traffic arrangements – diversions and the final designs are in progress at various locations of the Project at Kalamaria extension;
- Topographical works and works for the inventory of buildings and structures within the project influence zone are in progress.