- The works for the construction of piles for peripheral retaining, as well as excavation works at NEA KRINI Station have commenced;
- The preparation, review and approval of the designs for the relocation and diversion of PUO networks, the traffic arrangements-diversions and the final designs of the stations are at an advanced stage.
