- The execution of piling works is in progress (completed at a percentage of 35%) at the entrances/exits of VENIZELOS Station, while respective works at AGHIA SOFIA Station commenced.
- Archaeological finds were revealed at the southeastern side of SINTRIVANI Station.
- The excavation of the start-up shaft of the TBM in the area of NEOS SIDIRODROMIKOS STATHMOS will be soon completed (by now it is completed at a percentage of 92%).