Web Portal - Elliniko Metro A.E.
ΕΛΛΗΝΙΚΟ ΜΕΤΡΟ Α.Ε.ΕΛΛΗΝΙΚΟ ΜΕΤΡΟ Α.Ε.ΕΛΛΗΝΙΚΟ ΜΕΤΡΟ Α.Ε. logo espa
ΕΛΛΗΝΙΚΟ ΜΕΤΡΟ Α.Ε.ΕΛΛΗΝΙΚΟ ΜΕΤΡΟ Α.Ε.ΕΛΛΗΝΙΚΟ ΜΕΤΡΟ Α.Ε. logo espa
  • The construction of diaphragm walls at SINTRIVANI Station (completed at a percentage of 55%) and at DEMOKRATIAS Station (completed at a percentage of 35%) is at an advanced stage, while the installation of piles at the entrances/exits of VENIZELOS Station commenced.
  • Worksite installation of the contracting consortium at PAPAFI Station is in progress.
  • The construction of the diaphragm walls at the Line cross-over for the future extension to Stavroupoli is at an advanced stage (completed at a percentage of 46%).
Print Friendly, PDF & Email
WCAG