- The trial running ot the first Tunnel Boring Machine commenced.
- The construction of diaphragm walls is at an advanced stage:
- Forestation of NEOS SIDIRODROMIKOS STATHMOS:completed at a percentage of 95%
- DEMOKRATIAS Station:completed at a percentage of 91%
- SYNTRIVANI Station:completed at a percentage of 92%
- AGHIA SOFIA Station:completed at a percentage of 51%
- Branching towards Stavroupoli:completed at a percentage of 92%
- Works related to the construction of retaining piles at PANEPISTIMIO Station will be completed soon (they are now completed at a percentage of 91%).
- Excavation works (completed at a percentage of 16%) at the train stabling shed commenced at Neos Sidirodromikos Stathmos.