- The pile driving works at the TBM Start-up Shaft have been completed;
- The relocation of the Public Utility Organizations networks is in progress at AGHIA VARVARA Station;
- The archaeological survey is in progress at AGHIA VARVARA, NIKEA, KORYDALLOS and DIMOTIKO THEATRO Stations;
- The worksite occupation related works are in progress at Odyssos Square (PIRAEUS Station) and Korai Square (DIMOTIKO THEATRO Station).