AUGUST 2022

iso

TZAVELA Shaft

The following works have been completed:

  • Architectural finishes – Painting works at the staircase (walls, floors).
  • Construction of sound absorbing plaster.
  • Installation of staircase balustrades and balustrades at the street level staircase.
  • Installation of the entrance hatch at street level.
  • Installation of roller shutters.
  • Reinstatement of Tzavela and Lakonias Streets, opening to the

MANIATIKA STATION

STATION’s OPEN CUT      

The following works have been completed:

  • Surface reinstatement (construction of road pavement and sidewalks at Mavromichali Street).
  • Installation of glass panels at levels -1, -2.
  • Door painting works.
  • Installation of lifts at street level and at level -2.
  • Installation of lighting poles at the sidewalk of Etolikou Street.
  • Reinstatement of road pavement in Mavromichali Street at the west of the station.

 The following works are in progress:

  • Architectural finishes – Re-painting works at walls and floors at levels -4, -3, -2, -1, reinstatement of concrete surfaces, re-painting works of parapet walls at street level.
  • Installation of steel cladding (panels) on the walls/ceilings and of metal side covers at the station’s escalators.
  • Installation of stainless steel handrails.
  • Installation of the station’s signage.
  • Construction of partition walls at the station’s south expropriation limits (street level)
  • Surface reinstatement (construction of road pavement and sidewalks at Etolikou Street)
  • Slab paving works and installation of paving stones and lighting at street level.
  • Laying of planting soil at the station’s flower beds.
  • Connection of the station with EYDAP network.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

The following works have been completed:

  • Steel cladding on the roof and side covers.
  • Installation of information boards and signage at the platforms.
  • Installation of seats at the platforms.
  • Installation of radio communication (TETRA) cable.

UNDERGROUND NATM SECTIONS OF THE STATION (NATM)

The following works have been completed:

  • Installation of granites and stainless ducts (gutters).
  • Installation of lining (made of steel and gypsum boards) at the access tunnels of the station.
  • Installation of lifts glass panes.
  • Installation of metal side covers and handrails at the station’s escalators.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Construction of perimeter wall at the boundaries of the expropriation.
  • Construction of metal structures at K.P. +8.36 and +21.00.
  • Construction of sound absorbing plaster.
  • Installation of staircase balustrades – handrails.
  • Architectural finishes (re-painting works).
  • Door painting works.
  • Installation of access hatch at the street level.
  • Road surface reinstatement at Koumoundourou Street, installation of lighting bollards.

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Installation of metal structures at K.P. +8.08 and +24.98.
  • Construction of sound absorbing plaster.
  • Architectural finishes (re-painting works).
  • Door painting works.
  • Installation of staircase balustrades – handrails.
  • Installation of the entrance hatch at street level.
  • Construction of perimeter parapet walls at the boundary of the expropriation.
  • Road surface reinstatement at Dimitrakopoulou Street, installation of lighting bollards.

MELA SHAFT

The following works have been completed:

  • Concreting of pit.

 PIRAEUS STATION

The following works have been completed:

  • Concreting of main station.

The following works are in progress:

  • Construction of architectural finishes (filling works, installation of granites at levels -1 and -3, installation of false ceiling at levels -1 and -3, painting works at levels -1 and -2, at the staircases and at track level, installation of glass panes at level -1, wall and column cladding works at level -3 and side coverings at the public staircases, painting of doors and installation of their accessories, works in the LAS, RS areas.
  • Electromechanical works at levels -1 and -2.
  • Installation of granites and marbles at street level.
  • Installation of gutters, curbs and construction of sidewalks inside and outside the main worksite area and installation of ILPAP columns.
  • Installation of shaft grids.
  • Works for the construction of the asphalt sub-base to bring back the street above station level.
  • Network reinstatement works at street level (PPC, OTE, sewage, etc.)
  • Asphalt paving at the street section in front of the Suburban Railway Station.
  • Works for the installation of station lifts (frame – glass panes).
  • Installation of plant irrigation network and other reinstatement works at street level.
  • Installation of signs at the platform and ticket issuing levels.

ROLOI SHAFT & NATM ACCESS TUNNEL

 The following works have been completed:

  • Sealing of the temporary pumping station.
  • Installation of emergency exit hatch at street level.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:                                                                                 

  • Opening of V. Georgiou and Karaiskou Streets to the traffic.

The following works are in progress:

  • Reinstatement at street level.
  • Painting of the floor of the mechanical level.
  • Installation of false ceiling at the ticketing level and at the platform level.
  • Installation of floor granites at the ticketing level and at the platform level.
  • Installation of glass panes at the lift pits.
  • Construction of stainless cladding, stanchion and balustrades at the ticketing and at platform levels.
  • Installation of ironmongery on the doors.
  • Assembly-disassembly of building crane.
  • Conservation of the Project’s archaeological finds.

STAIRCASE GALLERIES

The following works are in progress:

  • Installation of supports and wall and ceiling panels.
  • Installation of handrails at the staircases.
  • Installation of floor granites.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Construction of lift housing structure at street level.

The following works are in progress:

  • Reinstatement at street level.
  • Installation of wall and ceiling panels according to the design for the display of the archaeological finds.
  • Implementation of the design for the display of the archaeological finds in the recess.
  • Wall-mounted granites at the staircase termination point at street level.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works are in progress:

  • Installation of wall and ceiling panels according to the design for the display of the archaeological finds.
  • Installation of granite floors.
  • Implementation of the design for the display of the archaeological finds in the recess.

DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY   

The following works have been completed:

  • Sealing of the temporary pumping station.
  • Sidewalk traffic reinstatement on V. Georgiou Street.

 The following works are in progress:

  • Reinstatement at street level.

 TRIPLE TRACK NATM TUNNEL

Works have been completed.

DELIGIANNI SHAFT

The following works have been completed:

  • Disassembly of building crane.

The following works are in progress:

  • Construction of parapet walls at the square.
  • Demolition of pile cap beam.
  • Backfilling-compaction works.

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works are in progress:

  • Reinstatement at street level.
  • Construction of shaft safety railing.
Print Friendly, PDF & Email