Piraeus Project progress

MARCH 2020

 

AGHIA VARVARA STATION

The following works are in progress:

  • Wall and columns cladding (metal, glass etc.)
  • Square reinstatement (granites, passageways)
  • Signage, signalling and lighting
  • Other reinstatement works at street level
  • Station signs and other signs.

MEGALOU ALEXANDROU SHAFT

The following works are still pending:

  • Planting (street level).

TAXIARCHON SHAFT

The following works are in progress:

  • Painting works
  • Configuration at street level.

KORYDALLOS STATION

The following works are in progress:

  • Wall and Columns cladding
  • Installation of false ceilings
  • Installation of balustrades
  • Installation of roller shutters
  • Installation of irrigation system at street level
  • Installation of signage
  • Installation of stainless steel structures
  • Repair of painted surfaces and worn granites
  • Installation of Station entrances’ sheds
  • Installation of lift at street level
  • Configuration at street level (Eleftherias Square)

PISSIDIAS SHAFT

Works have been completed.

NIKEA STATION

MAIN STATION

The following works are in progress:

  • Re-painting of cylindrical supports at level -3 of the platforms
  • Re-painting of technical rooms at various Station levels
  • Lining of roller shutter (ETALBOND) at the shed of the central entrance
  • Cladding of vertical items using metal panels
  • False ceilings
  • Installation of signage
  • Construction of sheds at the natural light shafts.

PIRAEUS STATION 

STATION

The following works have been completed:

  • Installation and prestressing of struts for temporary retaining up to level 5.
  • Installation of waterproofing and concreting of the foundation (bay 4).

The following works are in progress:

  • Installation of reinforcement and concreting at section 1
  • Station excavation at sections 2, 3 and 5 a, b (last phase)
  • Improvement and installation of waterproofing and reinforcement at sections 2, 3.
  • Installation and pre-loading of 4 struts of the temporary retaining at level 6.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works are still pending:

  • Door installation at the E/M floor.

The following works are in progress:

  • Masonry walls at ticketing level
  • Waterproofing at street level
  • Backfilling – compaction related works
  • Construction of bases of machinery at the E/M floor
  • Cleaning works

UNDERGROUND PART OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining, parapet walls and platform slab.

STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and works related to secondary concreting.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining and secondary concrete.

The following works are in progress:

  • Waterproofing of the top of the open trench.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level)
  • Secondary concrete at the staircases.

The following works are put on hold:

  • Secondary concrete at the access gallery.