The assembly of the 2nd TBM was completed and its trial running commenced. The construction of diaphragm walls was completed at SYNTRIVANI Station, while it is in progress at NEOS SIDIRODROMIKOS STATHMOS (completed at a percentage of 43%). The worksite installation was completed at ANALIPSI Station and works related to…