Month: March 2025

Καλαμαριά Ιανουάριος 2025

January 2025

NOMARCHIA Station (Station and Crossover): In progress are works for the transfer of switchboards intended for the Medium Voltage System, as well as works for the transfer of the batteries charger unit of the traction power system. MIKRA Station: In progress are the works related to the Medium Voltage distribution…
Μάθε Περισσότερα
Καλαμαριά Δεκέμβριος 2024

December 2024

• NOMARCHIA Station (Station and Crossover): In progress are works for the transfer of switchboards intended for the Medium Voltage System, as well as works for the transfer of the batteries charger unit of the traction power system. • MIKRA Station: In progress are the works related to the Medium…
Μάθε Περισσότερα
Καλαμαριά Νοέμβριος 2024

November 2024

Works for the upgrading of the PSD earthing system, as well as inspection works for the installation of the fire detection system are being executed in all stations.  Moreover, preparatory works for the installation of fibre optics are being executed. NOMARCHIA Station: In progress are the Medium Voltage System related…
Μάθε Περισσότερα
Καλαμαριά Οκτώβριος 2024

October 2024

NEA KRINI Station: In progress are the architectural finishes (walls and ceiling cladding, surfaces painting, stainless steel finishes) related works. MICRA Station: In progress are the architectural finishes (walls and ceiling cladding, surfaces painting, stainless steel finishes) related works, the fire detection system cabling inspection works, as well as road…
Μάθε Περισσότερα