Month: June 2024

Καλαμαριά Μάιος 2024

May 2024

KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, the installation of glass panes at stainless steel rails, as well as works for the installation of PSN tiles at level (-1). ARETSOU Station: Completed are works for the stripping of Kanari Street, while…
Μάθε Περισσότερα
Θεσσαλονίκη Μάιος 2024

May 2024

• NEW RAILWAY Station: Completed are the works for the installation of elevated floors at technical rooms, works for the installation of false-ceilings, works for the electrical connections of the mimic panels of the tunnel ventilation and ventilation/air-conditioning systems, works for the connection of cables of the BACS equipment, works…
Μάθε Περισσότερα
Καλαμαριά Απρίλιος 2024

April 2024

• KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, as well as works for the installation of PSN tiles at levels -1 and -2. • ARETSOU Station: In progress are the reinstatement works at street level, as well as works for the…
Μάθε Περισσότερα
Θεσσαλονίκη Απρίλιος 2024

April 2024

• NEW RAILWAY Station: Completed are the works for the installation of stainless steel and the testing of the low voltage distribution system. In progress are architectural finishes works at the western shaft, works for the electrical connections of the mimic panels of the tunnel ventilation and ventilation/air-conditioning systems, works…
Μάθε Περισσότερα
Καλαμαριά Μάρτιος 2024

March 2024

KALAMARIA Station: In progress are works for the installation of glass panes at stainless steel rails, PSN tiles at the platform level and at level -2. Moreover, in progress are the works for the installation of cladding at the external escalators. ARETSOU Station: In progress are the reinstatement works at…
Μάθε Περισσότερα
Θεσσαλονίκη Μάρτιος 2024

March 2024

• NEW RAILWAY Station: Completed are the works for the reinstatement of the southern section of Monastiriou Street, works for the construction of the terminations of the west shaft, as well as the installation of stainless steel balustrades at street level. Moreover, the LAS has been activated. In progress are…
Μάθε Περισσότερα
Καλαμαριά Φεβρουάριος 2024

February 2024

• NOMARCHIA Station (Station and Crossover): In the area of the Crossover, completed are the works for the installation of the elevated floor in the signalling equipment room. • KALAMARIA Station: In progress are works for the installation of glass panes at stainless steel rails, PSN tiles at the platform…
Μάθε Περισσότερα
Καλαμαριά Ιανουάριος 2024

January 2024

• NOMARCHIA Station: In progress are works for the implementation of the final traffic reinstatement (configuration of sidewalks at Andrianoupoleos street) as well as works for the installation of stainless steel balustrades and glass panes on stainless steel rails at the platform level. • KALAMARIA Station: In progress are works…
Μάθε Περισσότερα