Year: 2024

Καλαμαριά Ιούλιος 2024

July 2024

• NOMARCHIA Station (Station & Crossover): In the Crossover area, in progress are works for the installation of tiles, as well as works for the waterproofing of the water tank. • ARETSOU Station: In progress are works for the installation of floor granites at the platform level. • MICRA Station:…
Μάθε Περισσότερα
Θεσσαλονίκη Ιούλιος 2024

July 2024

• NEW RAILWAY Station, DIMOKRATIAS Station, AGIAS SOFIAS Station, SINTRIVANI Station, PANEPISTIMIO Station, PAPAFI Station, EFKLIDIS Station, FLEMING Station, ANALIPSI Station, 25 MARTIOU Station, VOULGARI Station, NEA ELVETIA Station: In progress are the BACS related testing activities of all installed electromechanical systems. • VENIZELOU Station: Completed are the works for…
Μάθε Περισσότερα
Καλαμαριά Ιούνιος 2024

June 2024

NOMARCHIA Station: Completed are works for the reinstatement of sidewalks and bollards for the protection of pedestrians on Mitropolitou Kydonion street. KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, as well as works for the installation of PSN tiles at level 0.…
Μάθε Περισσότερα
Καλαμαριά Μάιος 2024

May 2024

KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, the installation of glass panes at stainless steel rails, as well as works for the installation of PSN tiles at level (-1). ARETSOU Station: Completed are works for the stripping of Kanari Street, while…
Μάθε Περισσότερα
Θεσσαλονίκη Μάιος 2024

May 2024

• NEW RAILWAY Station: Completed are the works for the installation of elevated floors at technical rooms, works for the installation of false-ceilings, works for the electrical connections of the mimic panels of the tunnel ventilation and ventilation/air-conditioning systems, works for the connection of cables of the BACS equipment, works…
Μάθε Περισσότερα
Καλαμαριά Απρίλιος 2024

April 2024

• KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, as well as works for the installation of PSN tiles at levels -1 and -2. • ARETSOU Station: In progress are the reinstatement works at street level, as well as works for the…
Μάθε Περισσότερα